Carry out the following steps:
8.
Activate the solenoid valves in succession via the PLC in order to check the
proper function of the T.VIS M-20 FDD feedback signals.
9.
The I/O test can take place parallel to commissioning.
®
This completes commissioning.
7.4
Service Function
If maintenance must be conducted on a process valve that is fitted with a control
top T.VIS M-20 FDD, the valve core must be pulled out of the housing. For this
purpose, the valve disk pretension of the process valve must be relieved by
actuating the main actuator.
Another option with the hood removed is the manual override on the solenoid
valve, see “Control top with solenoid valves” .
Start-up
Service Function
430BAL014475EN_2
03.09.2021
37