GE WattStation Wall Mount Скачать руководство пользователя страница 1

GE Energy

WattStation

TM

 Wall Mount: Installation Guide

Plug-in Version

imagination at work

Before Installation:

WattStation should be installed only by a licensed 

contractor, and/or a licensed electrician in accor-

dance with all applicable state, local and national 

electrical codes and standards.

•  Ensure that a dedicated circuit, capable of supplying  

  30A at 208-240 VAC, is available
•  Power feed must have a centrally grounded neutral in  

  order for WattStation to function correctly.
•  Wall receptacle must be a NEMA 6-50 outlet.  

  A recommended 40A upstream circuit breaker, located 

  either in a panelboard or load center, should be used
•  Distance between the wall power receptacle and  

  WattStation mounting should be less than one (1) foot
•   Wall power receptacle with a weatherproof locking cover  

is required

•  Recommended mounting hardware for wood studs are  

  3/8” x 2” hex head lag bolts
•   Recommended mounting hardware for concrete walls  

are 3/8” x 1-3/4” concrete hex screws or 3/8” x 1-7/8” 

concrete anchors

Installation Instructions: 

Step 1:  Carefully unwrap the packaging and make sure  

the following items are present:
 

-  Wall Mounted WattStation unit

 

-  Mounting wall bracket

 

-  Template for wall-mounting holes

 

-  Key for WattStation mounting lock  

 

  (stored inside WattStation unit)

Step 2:  Check for any damage to the unit, the cord or the  

connector. If no damage is noticed, proceed to step 3. If  

damage is noticed, call 1-888-GE-RESOLve.

Step 3:  Install wall mount bracket to the wall. Use the  

provided template to locate wall-mounting holes to ensure 

hole locations match the bracket. Distance from floor to 

bottom of wall mount bracket should be 18” minimum for 

indoor use and 24” minimum for outdoor use. Distance to the 

top of the unit should be 48” maximum for all applications 

per NEC 625.29. For ADA compliant installation, refer to ADA 

accessibility guidelines, section 4.2.

STEP (3 PI & HW)

WARNING: Danger of electrical shock or injury. Turn 

OFF power at the panelboard or load center before 

working inside the equipment or removing any  

component. Do not remove circuit protective devices or 

any other component until the power is turned OFF.