2.

 

DESIGN AND CONSTRUCTION 

2.1.

 

Construction and primary circuit 

 

The  active  part  of  the  voltage 
transformer  is  located  below  the 
porcelain  insulator  and  the  current 
transformer  part  above.  The  primary 
circuit  is  short,  rigid  and  straight, 
minimizing  heating.  In  addition,  it 
withstands  electrodynamics  forces 
more  easily,  allowing  high  level 
performance, 

related 

to 

electrodynamics and thermal effects, in 
a presence of short-circuit currents.  
 
Primary series and parallel connections 
with external links (for reconnection 1:2 
or  1:2:4)  or,  if  necessary,  n-turn  (more 
than  4  turns)  designs  can  be  provided. 
This  arrangement  allows  also  better 
accuracy in transient conditions. 
 
The  primary  terminals  are  directly 
connected to the conductor. 

Attention! Do not lift the unit at the 
primary  terminals  or  remove  the 
primary terminals! 

2.2.

 

Secondary circuit 

 

Related  to  the  CT’s  active  part, 

the 

toroidal  ferromagnetic  cores  are 
manufactured  either  from  very  high 
permeability  grain-oriented  steel  or 
from  specialized  alloys.  In  order  to 
achieve 

satisfactory 

transient 

behavior,  protection  cores  can  also  be 
provided with gaps. 
 
All  secondary  windings  are  enclosed  in 
an  aluminum  box  which  protects  them 
against  high  frequency  disturbances 
while  acting  as  a  low  voltage  shielding 

electrode.  This  aluminum  box  is 
extended up to the base by an aluminum 
tube which contains all secondary leads. 
The  cross  section  of  the  earth 
connections is designed to support fault 
currents. 
 
The  bottom  of  the  hermetic  and 
watertight  secondary  terminal  box  is  
closed by a fitted plate, with or without 
cable  gland  depending  on  customer 
requirements. 
 

2.3.

 

Paper-oil insulation 

 
The  active  part  of  the  transformer  is 
insulated  by  a  vacuum  impregnated 
oil/paper system. Degassed and filtered 
mineral oil is used and is heated before 
filling 

to 

provide 

maximum 

impregnation. It is an insulating oil with 
excellent  aging  stability  and  gas 
absorbing  properties. 

It  does  not 

contain any Polychlorinated Biphenyl 
(PCB).

 

2.4.

 

Oil volume compensation system 

 
To protect the oil from the environment, 
the  CT  head  is  sealed  by  a  metallic 
bellows. The bellows assembly provides 
pressure compensation for temperature 
variation and allows the transformer to 
work virtually free of over-pressure.  
The bellows resists aging and corrosion. 
 

IF THE HERMETIC SEAL OTHER THAN 
DURING  OIL  SAMPLING  IS  BROKEN, 
CONTACT  THE  MANUFACTURER 
IMMEDIATELY. 
 

An  oil  level  indicator  is  provided  and  is 
scaled  to  show  the  oil  level  over  the 

Содержание KOTEF 72.5

Страница 1: ...GE Grid Solutions INSTRUCTION MANUAL MIITR102 COMBINED INSTRUMENT TRANSFORMER KOTEF 72 5 245...

Страница 2: ...Instruction Manual GE Grid Solutions 2 GE Grid Solutions Av Nossa Senhora da Piedade 1021 37504 358 Itajub MG Brasil AIB 00 07 28 21 FML FES Owner revision Date Prepared Approved...

Страница 3: ...as the inherent capacitance may have electric charges with voltage at the lethal level In addition a ground rod should stay on the line terminal as long as people work on the unit In the event an elec...

Страница 4: ...3 3 Unpacking 8 3 4 Storage 9 4 BELLOWS BLOCKING SYSTEM AND ASSEMBLY IN THE STRUCTURE 9 4 1 Bellows blocking system 9 4 2 Assembly in the structure 10 5 CONTACT SURFACES PREPARATION 10 6 CONNECTIONS 1...

Страница 5: ...to the picture below 1 Top Cover 2 Oil Level Indicator metallic bellows 3 Primary Reconnection Terminals 4 Primary terminals aluminum or copper 5 CT Headhousing current transformer part 6 Porcelain or...

Страница 6: ...All secondary windings are enclosed in an aluminum box which protects them against high frequency disturbances while acting as a low voltage shielding electrode This aluminum box is extended up to the...

Страница 7: ...t mounted to the crate skid and the head resting on damping foam For overseas shipment the CIT is packed in wooden crates designed according to SEI cat 4 specification The crates can be stacked but no...

Страница 8: ...extremities Attention NEVER lift a transformer by its primary terminals Lift it by the lifting eyes on the transformer top All four lifting eyes must be used during lifting operation To lift the tran...

Страница 9: ...tly compressed by the top cover A protection of plastic film is also put in place around the bellows to protect it against contact with the top cover In order to remove the blocking system place the t...

Страница 10: ...with sandpaper 150 grain in order to eliminate the oxidation layer Scrub the contact surfaces with a metallic brush diameter of the thread 0 3mm and impregnate with grease of the type PENETROX or equi...

Страница 11: ...peration 6 5 Terminal marking Primary and secondary terminal marking are done according to the specified standard please refer to the set of drawing Primary and secondary connection scheme are shown o...

Страница 12: ...s taken in the factory are important as so the measurements during commissioning of each transformer The comparison between test results measured at the field allows following the evolution of each pa...

Страница 13: ...tion and thereafter at four year intervals depending on availability of the 1 Ratio TTR 2 Polarity Polarity meter 3 Saturation Voltage ac voltage source Voltmeter and Ammeter 4 Ohm Resistance Wheatsto...

Страница 14: ...ndfill properly licensed Other materials Industrial landfill properly licensed The disposal of oil and components contaminated with oil directly into the soil or water is prohibited For further inform...

Отзывы: