Confirm that the secondary circuit of 
the  voltage  transformer  part  is  not 
shorted. 
 
Make sure that no secondary winding 
of  the  current  transformer  part  is 
open circuited. 

 

Verify  the  correct  position  of  the 
primary  terminal  (transformer  with 
reconnection primary bars). Refer to 
the set of drawing. 

 

Verify that the oil level indicator is in 
the green strip area. 

 

Whilst  all  care  is  taken  in  the  factory 
during  oil  filling,  the  surface  near  of 
screws  and  bellows  could  have  a  small 
quantity  of  oil.  This  shall  not  be 
considered  as  an  oil  leakage  provided 
the  bellows  are  positioned  within  the 
green strip area. 

 

It  is  not  necessary  to  remove  oil 
samples  for  analysis.  The  CIT  is 
hermetically sealed 

 

If  required,  small  quantity  of  oil  can  be 
taken.  Always  verify  oil  level  indicator 
before take oil samples. 
 

Never  complete  oil  volume  without 
prior formal authorization of GE. 

 

Important remark

During 

commissioning, 

it 

is 

recommended  to  register  the  values 
acquired for each of the performed tests 
in  order  to  compare  with  future 
measurements during the CIT

’s

 lifetime. 

The measurements taken in the factory 
are important as so the measurements 
during 

commissioning 

of 

each 

transformer.  The  comparison  between 

test results measured at the field allows 
following  the  evolution  of  each 
parameter.  

 

9.

 

MAINTAINENCE AFTER ENERGIZING 

 
Besides  regular  cleaning  of  the 
transformer  surface  and  especially  the 
insulator,  no  routine  maintenance  is 
required on the transformers. However, 
the oil level indicator position should be 
checked  regularly,  along  with  visual 
inspections 

during 

the 

normal 

scheduled  maintenance  periods.  It  is 
good  practice  to  compare  the  oil  level 
indicator  position  of  neighboring  units. 
Also, the inside of the terminal box and 
the  ventilation  screens  should  be 
checked for cleanliness.  
After  installation  and  energizing,  the 
transformers  shall  not  require  any 
further  intervention.  However,  it  is 
suggested performing visual inspections 
during the first weeks of service in order 
to: 

 

Verify if there is no oil leakage near the 
fixation  base  and  secondary  terminal 
box. 
 
With an infrared imaging device, check if 
the  primary  terminal  connections  are 
not  overheating.  Compare  with  other 
CITs in the same circuit. 

 

After one year of operation, it is advised 
a  detailed  inspection  of  tightening 
torques  and  oil  leakage  and  thereafter 
twice  per  year  according  to  the 
substation maintenance contract.  
 

Содержание KOTEF 72.5

Страница 1: ...GE Grid Solutions INSTRUCTION MANUAL MIITR102 COMBINED INSTRUMENT TRANSFORMER KOTEF 72 5 245...

Страница 2: ...Instruction Manual GE Grid Solutions 2 GE Grid Solutions Av Nossa Senhora da Piedade 1021 37504 358 Itajub MG Brasil AIB 00 07 28 21 FML FES Owner revision Date Prepared Approved...

Страница 3: ...as the inherent capacitance may have electric charges with voltage at the lethal level In addition a ground rod should stay on the line terminal as long as people work on the unit In the event an elec...

Страница 4: ...3 3 Unpacking 8 3 4 Storage 9 4 BELLOWS BLOCKING SYSTEM AND ASSEMBLY IN THE STRUCTURE 9 4 1 Bellows blocking system 9 4 2 Assembly in the structure 10 5 CONTACT SURFACES PREPARATION 10 6 CONNECTIONS 1...

Страница 5: ...to the picture below 1 Top Cover 2 Oil Level Indicator metallic bellows 3 Primary Reconnection Terminals 4 Primary terminals aluminum or copper 5 CT Headhousing current transformer part 6 Porcelain or...

Страница 6: ...All secondary windings are enclosed in an aluminum box which protects them against high frequency disturbances while acting as a low voltage shielding electrode This aluminum box is extended up to the...

Страница 7: ...t mounted to the crate skid and the head resting on damping foam For overseas shipment the CIT is packed in wooden crates designed according to SEI cat 4 specification The crates can be stacked but no...

Страница 8: ...extremities Attention NEVER lift a transformer by its primary terminals Lift it by the lifting eyes on the transformer top All four lifting eyes must be used during lifting operation To lift the tran...

Страница 9: ...tly compressed by the top cover A protection of plastic film is also put in place around the bellows to protect it against contact with the top cover In order to remove the blocking system place the t...

Страница 10: ...with sandpaper 150 grain in order to eliminate the oxidation layer Scrub the contact surfaces with a metallic brush diameter of the thread 0 3mm and impregnate with grease of the type PENETROX or equi...

Страница 11: ...peration 6 5 Terminal marking Primary and secondary terminal marking are done according to the specified standard please refer to the set of drawing Primary and secondary connection scheme are shown o...

Страница 12: ...s taken in the factory are important as so the measurements during commissioning of each transformer The comparison between test results measured at the field allows following the evolution of each pa...

Страница 13: ...tion and thereafter at four year intervals depending on availability of the 1 Ratio TTR 2 Polarity Polarity meter 3 Saturation Voltage ac voltage source Voltmeter and Ammeter 4 Ohm Resistance Wheatsto...

Страница 14: ...ndfill properly licensed Other materials Industrial landfill properly licensed The disposal of oil and components contaminated with oil directly into the soil or water is prohibited For further inform...

Отзывы: