background image

CP Converter Shelf - Quick Start Guide 

Document 850033106   r04   2015 April 

Shelf: J2007001 L014 CC109157657 

 

 

DC input from left and right 

 L015 

150042727 

 

 

DC input from left only 

Converters: CP2000DC54PEZ  CC109162104 

CP2500DC54PEZ CC109170528 

 

Controller: CP841_3C3R 

CC109145331 

CP Converter Shelf System –48V

 

Quick Start Guide 

GE

 

Critical Power

 

 

No vertical spacing is required, allow a minimum 2 inch clearance at back of shelf for rectifier airflow. 
Refer to 

Compact Power Line (CPL) Brochure

 for details and accessories. 

Step 2 - Connect Chassis Ground 

Some applications may rely on frame mounting screws for shelf 

ground omitting the chassis ground cable.  

Minimum 6 AWG wire is recommended. 
Lugs - 1/4” on 5/8” centers (not provided). 

Torque to 65 in-lb (7.3 Nm) - 7/16” socket. 

Step 1 - Mount Shelf 

1.  Reposition mounting ears as required - 8 screws each.  

Torque to 25 in-lb (2.8Nm) - Phillips screwdriver. 

2.  Attach shelf to the frame using a minimum of four screws (two 

on each side) - 12-24 (provided).  

Torque to 35 in-lb (4Nm) - 5/16” socket. 

Chassis 

Ground 

Output Return (Ground) 

-48V Output 

DC Inputs - Converter Inputs 

POS NEG 

NEG POS 


 


 

Step 3 - Connect -48V Output and Output Return 

Lugs - 1/4” on 5/8” centers (not provided). 

Torque to 65 in-lb (7.3 Nm) - 7/16” socket. 

Step 4 - Connect DC Inputs 



Feed each input from 80A breaker (shelf rating limited) 

 

Lugs - 1/4” on 5/8” centers (not provided). 

Torque to 65 in-lb (7.3 Nm) - 7/16” socket 

 

CAUTION

: Verify DC Input voltage and polarity with a voltmeter 

before proceeding. 

Note

:  Input Feed Returns must be externally connected to DC 

Reference (CO) ground. 

Tools required: 

 

Wire cutters and strippers 

Torque wrench - 0-65 in-lb (0-10Nm) 

Cable crimpers 

Sockets - 5/16”, 7/16, etc. 

 
Screwdrivers - Philips #1 and #2, Flat small 

 

L014 shown 

(L015 has all DC input feeds from the right as viewed from the rear) 

Содержание J2045J389E

Страница 1: ...sition mounting ears as required 8 screws each Torque to 25 in lb 2 8Nm Phillips screwdriver 2 Attach shelf to the frame using a minimum of four screws two on each side 12 24 provided Torque to 35 in lb 4Nm 5 16 socket Chassis Ground Output Return Ground 48V Output DC Inputs Converter Inputs POS NEG NEG POS 1 2 4 3 Step 3 Connect 48V Output and Output Return Lugs 1 4 on 5 8 centers not provided To...

Страница 2: ...ery Temp and Voltage Monitor to J3 Step 8 Install 1 Wire Battery Temp and Voltage Monitor per Galaxy Pulsar Edge Controller Quick Start Guide Optional Step 9 Install Converter s Latch 1 Slide converter into its slot approximately 3 4 of the way 2 Open the faceplate by sliding the faceplate latch to the left until the faceplate releases and swings outward 3 Slide the unit into the slot until it eng...

Страница 3: ... Alrm 4 J2 All Controllers Controller Information Alarm Connections See the Compact Power Line Brochure for details Alarm connections are on the rear of the shelf J1 is Alarm Outputs and J2 is Alarm Inputs Change alarm descriptions via LAN port Web pages or Craft port EasyView2 when required J1 1 Includes a mixture of Alarm Inputs and or Alarm Outputs de pending on the controller model 2 Connector...

Страница 4: ...ng Network Connect to an Isolated Ground Plane Isolated Bonding Network or an Integrated Ground Plane Mesh Bonding Network or Common Bonding Network Installation Environment Install in Network Telecommunication Facilities OSP or where NEC applies DC return may be either Isolated DC return DC I or Common DC return DC C Reference Documents These documents are available at www gecriticalpower com Doc...

Отзывы: