Mount the main part tubing
Action
Step
7
1
2
3
4
6
5
Pinch valves:
Insert the tubing into the air trap
valves (1-3 in figure), the column
valves (4-6), and the air release
valve (7). Proceed in the order
indicated by the numbers in the
figure (i.e., start with the air trap
valves).
1 A
Close the valve safety locks as
you proceed.
1 B
Note:
Make sure the pH cable does not get trapped behind the tubing. The cable
should be attached to its holder on the cabinet.
Pressure cells:
Attach the three pressure cells
(for sensors PT-111, PT-112, and
PT-113) by pushing them onto
their respective pressure cell
adapters on the cabinet.
2 A
Secure the cells by turning the
latch over the pressure cell
body, and fasten the screws.
2 B
Before firmly fastening the
screws, check that the cell is
correctly positioned and that
there is no gap between the cell
body and the adapter. Apply
finger force only.
2 C
ÄKTA ready Operating Instructions 28960345 AD
91
6 Flow kit installation
6.3 Mounting the flow kit