Start-Up and Test
MDE-4339 9820Q ASTRA Installation/Operation • July 2004
37
Start-Up
After successfully verifying the installation against the completion checklist, the unit is ready for
start-up. Follow the procedure below to perform an orderly start-up of the Series 9820Q.
1.
Verify that all switches on the CPU PCB are set properly for the various operating conditions
as explained in Section 5.
2.
Turn on the circuit breakers for the microprocessor.
3.
Authorize the unit through the fuel management system, if available.
4.
Remove the nozzle from its holder and turn on the pump handle. Verify that the display goes
through the proper reset sequence as explained in Section 5,
Operating Sequence
.
Note: when power is turned on for the register, you must reset the handle twice to go through
the reset sequence.
5.
Dispense fuel. Verify that the high flow valve opens, if equipped. Check all plumbing for
leaks at this time.
6.
Turn the pump handle off. Open the nozzle. No fuel should be dispensed at this time.
7.
Verify that the correct quantity was recorded by the fuel management system, if available.
8.
Run the unit through all standard calibration procedures.
9.
Reset the electronic totalizer as described in
View/Reset Totalizer
in Section 5.
Post Start-Up Tests
Voltage
The incoming voltage to the pump should be checked and any reading not within 10% of rated
voltage should be corrected before testing is continued. It is good practice to take voltage readings
while the pump is operating on bypass and also while making a delivery. Any voltage drop in
excess of 10% during either of these operating states should be considered a low voltage condition.
Corrective action should be taken to insure an adequate power supply to the pump.
Tightness
After determining that the pump is operating satisfactorily and the system is fully primed, check
the pump and piping to make sure that all connections are tight.
Belts
Since belts do stretch slightly during the first few minutes of operation, check the belt tension after
completing the operational test; a properly tightened belt will permit twisting the belt 180 degrees
midway between the motor and pump pulleys.
On the 9822Q and 9823Q, the belt can be tightened by loosening the cap screw which holds the
idler arm and sliding the arm to obtain the correct belt tension of 6-3/4 lbs. (+ 3/4). When the
adjustment is complete, remember to retighten the cap screw.
Calibration
All GASBOY pumps are adjusted for accurate measure at the factory. However, since the
conditions of the installation can affect pump accuracy, it is the responsibility of the installer to
check the pump for accuracy and make any needed adjustments.
Where required
, it is the owner's
responsibility to report this device to the local Weights and Measures officials for their inspection
before the unit is put into service.
Each meter is equipped with a mechanism for calibration, located on the side of the meter. To
adjust the volume dispensed:
Содержание 9822Q
Страница 1: ...Series 9820Q ASTRA Installation Operation Manual MDE 4339 formerly 035090...
Страница 18: ...GASBOY Series 9820Q 12 MDE 4339 9820Q ASTRA Installation Operation July 2004...
Страница 22: ...GASBOY Series 9820Q 16 MDE 4339 9820Q ASTRA Installation Operation July 2004...
Страница 32: ...GASBOY Series 9820Q 26 MDE 4339 9820Q ASTRA Installation Operation July 2004...