MDE-4864B Gasboy® 9820 Pump Interface Kits Installation Instructions · March 2022
Page 5
Installation of the Gasboy 9820 Pump Interface Kit
Installation of the Gasboy 9820 Pump Interface Kit
Installing this kit involves DC wiring to the Fuel Management System. Refer to
MDE-4567
9120K & 9820K Series AST Pumps Installation and Operation Manual
, and your Fuel
Management System Installation Manual before proceeding.
To install the Gasboy 9820 Pump Interface Kit, proceed as follows:
1
Turn off the circuit breakers that supply power to the MICRO and PUMP feeds.
2
Unlock the door and loosen the two screws. Tilt the top of the door out, then lift up to remove
it.
Figure 1: Removing the Door
Loosen the Screws
Unlock
the
Door