CHAPTER 4
ETSI Configuration
Connecting and Checking Office Battery to the PDP
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
4-22
Fujitsu and Fujitsu Customer Use Only
DAN
G
ER:
Carefully follow the instructions in this section to avoid personal injury, damage to the
equipment, or both. Installing power cables that are already connected at one end to a
voltage source can result in an electrical accident.
Step
Task
1
Verify that the office-battery ends of the power cables are not connected to the office batteries.
These connections are the last to be made after the PDP has been installed. If necessary, follow
local procedures to disconnect office power from these cables or remove fuses from the rack
PDP. Use a DMM to ensure that the voltage is 0 V DC (with reference to the battery ground)
at the equipment-rack end of the cables.
Note:
For FLASHWAVE 7500 equipment, fuses should be sized to ensure that the maximum input
current does not exceed 80 percent of the fuse size. Use 30 A fuses to ensure that this requirement is
met for all configurations of the FLASHWAVE 7500 equipment.
2
Remove the protective covers that protect the A/B battery terminals at both ends on the PDP
panel. See
for the PDP.
3
Remove the top nuts and washers from the threaded studs for all + and - connections being
installed.
4
Locate the double-lug connector on the PDP end of the power cable that is to be connected to
battery source A1 at the end of this procedure.
5
Place the single two-hole lug on the two A1 - studs so that the cable is easily routed toward the
outside edge of the shelf.
Note:
A washer may be required as a standoff between the circuit breaker panel and the lug.
6
Install the washer and nut and tighten according to local standards.
7
Locate the single two-hole lug on the PDP end of the power cable that is to provide the return
for battery source A1 at the end of this procedure.
8
Place the single two-hole lug on the two A1 + studs so that the return cable is easily routed
toward the outside edge of the shelf.
Note:
A washer may be required as a standoff between the circuit breaker panel and the lug.
9
Install the washer and nut and tighten according to local standards.
Revision 1, June 2009
Содержание FLASHWAVE 7500
Страница 8: ...Revision 1 June 2009 ...
Страница 10: ...Revision 1 June 2009 ...
Страница 16: ...Revision 1 June 2009 ...
Страница 362: ...Revision 1 June 2009 ...
Страница 386: ...Revision 1 June 2009 ...