Installation Introduction 

I. Site Preparation 

When a suitable installation location is identified, you will need to determine if the system will be mounted 
horizontally as recommended, or vertically if necessary (if mounting vertically, the outlet will need to be at 
the top and a TRV is required). Allow adequate space for the ongoing maintenance and pre-plan the 
plumbing so that the ports will be facing up. 

II. Mounting 

When mounting the system on a wall, mark out the approx. location of each wall bracket. Fix a bracket to 
the wall and using a level and ruler, mark out the appropriate location for the second bracket. Brackets 
should ideally have the pivot/hinge at the bottom and screw to close the bracket at the top. Hold the 
Chamber in firmly to the brackets and they do up one of the clamps to secure the system. A second set of 
hands can assist to make this easier. 

III. Installing Connections 

The UV systems are manufactured with male BSP threads either in 1” (GT7-8K/9K/16K) or ½” (GT7-4K). 
The smaller GT7-

2K unit is ¼” Female. Use appropriate plumbing fittings to install onto the chamber for 

adapting to your plumbing. 

IV. Thermal Relief Valve 

A Thermal Relief Valve is a valve with a build in sensor that will open and drain water once the temperature 
in the chamber reaches 56°C. 

A Thermal Relief Valve is also recommended on installations where there can be prolonged periods of time 
without water flow. Generally lower wattage systems (<40W) do not reach extreme temperatures under 
normal conditions; however, it is best to install a TRV to limit the temperature.   

When installing a TRV, note the below requirements: 

  The TRV must be installed on the Outlet of the UV System (which should be the open end). 

 

The TRV tube must be allowed to drain freely without head pressure (don’t run the tubing vertically). 

  The TRV operates from temperature so always have the ports facing up (heat rises). 

  When vertical system installation is required, make sure the valve itself is also facing up. 

The valve will open at 56°C and Close at ~ 54 

– 55°C, if you have a pump without a bladder and a very 

sensitive high/low pressure switch, you may notice the pump cycling as the valve activates/deactivates 
during prolonged periods without flow. 

V. Filter Protection 

As per Australian Plumbing Codes, a pressure limiting valve should be installed to limit the pressure to 500 
kPa when the feed pressure exceeds 500 kPa. If Water Hammer is present, install a suitable Water 
Hammer Arresting device. 

Commissioning & Start-up 

I. Quartz Thimble Installation 

Due to the fragile nature of the quartz, care must be taken when handling and installing the thimble and 
lamp. The below steps are for horizontal installations. 

1.  Remove the knurled nut from the end of the SS chamber. 
2.  Wearing clean gloves or handling with a micro-fibre cloth, remove the thimble from the packaging 

and check for any marks or blemishes. Insert the glass thimble into the 
chamber at the open end. The thimble will need to go into the chamber 
by the domed end first. At the rounded end of the UV SS chamber, you 
will find a locating port to accommodate the dome end of the quartz tube 
(On the GT7-8K/9K System, this will be a spring). Carefully push the 
quartz thimble into this port so the lamp is securely seated. 

Содержание GT7- 16K

Страница 1: ...ements 3 VI What is Ultraviolet Sanitation 3 VII Example Applications 3 Installation Introduction 4 I Site Preparation 4 II Mounting 4 III Installing Connections 4 IV Thermal Relief Valve 4 V Filter P...

Страница 2: ...must be followed closely to prevent serious personal injury Ensure eye protection is worn when servicing and installing this unit to protect from harmful UV C Radiation This radiation can be harmful...

Страница 3: ...ounding plumbing must be earthed to prevent electrolysis which will cause corrosion VI What is Ultraviolet Sanitation Ultraviolet sanitation works by breaking down the cell wall of a micro organism al...

Страница 4: ...to install a TRV to limit the temperature When installing a TRV note the below requirements The TRV must be installed on the Outlet of the UV System which should be the open end The TRV tube must be a...

Страница 5: ...last Operation GT7 8K PS The 10W 40W ballast is straightforward for operation It features a lamp status failure indicator light along with an audible alarm should there be a fault The ballast will aut...

Страница 6: ...ow the lamp to fire Do not look directly at the lamp without eye protection c Confirm that the lamp lights up correctly and the ballast is showing a green light to signify that the lamp is running cor...

Страница 7: ...ough Thus we recommend replacing the lamp every 12 months and the thimble every 1 2 years Lamp Replacement Every 12 Months GT7 2K Lamp 14W Replacement UV Lamp Suit GT7 2K GT7 4K Lamp 20W Replacement U...

Страница 8: ...et a chance to cool down effectively If there are significant fluctuations in usage or flow rates it is good practice to install a thermal relief valve sold separately on the outlet of the UV chamber...

Страница 9: ...arranty period please contact the manufacturer for further instructions 2 Check the wall socket with a different electrical appliance to check if the GPO is functioning Also check your circuit breaker...

Страница 10: ...plumber The consumer is responsible for keeping record and proof of installation in the form of an invoice and or receipt Filter systems must be maintained as per FSA recommendations including the us...

Страница 11: ...warranty is subject to terms and conditions outlined below This extended warranty covers the below parts of the system Ultraviolet Chamber 316 Stainless Steel Extended Warranty Qualification Extended...

Отзывы: