background image

Installation Instructions

The ceiling enclosure is designed to be mounted on a suspended ceiling grid of  2x2ft or 60x60cm ceiling tiles.

 

If the 

enclosure is to be installed in a 2x4ft or 60x120cm grid, the tile will first need to be cut.

1.   Secure provided cables to ceiling structure with anchors appropriate for the ceiling structure type.

  

(Anchors not provided)

 

 WARNING

Failure to properly set anchors may result in failure of anchor and serious personal injury or 

damage to equipment!

2.   Loop cables through cable anchors and tighten  

so there is no slack at the anchor. 

Image 1

3.   Remove one ceiling tile from ceiling where the  

enclosure will be mounted. If using in 2x4ft or  
60x120cm grid, cut the tile to fit the space next  
to the ceiling enclosure.

4.   Close and lock (or remove) the lid on the ceiling  

enclosure to ensure that it does not swing open 
during installation.

5.   Place enclosure on top of grid while still supporting  

it until cables are attached in step 6.

 Image 2 

Be sure to orient the enclosure for easy cable  
routing to power, projector, wall plates, etc.

FrontRow PlenumCore Installation

Warning

Failure to follow these instructions can result in serious personal injury or damage to equipment.

Installation should only be completed by a qualified installer.

It is the installer’s responsibility to make sure the structure to which this component is attached can support five 
times the combined weight of the enclosure and all equipment it contains. Reinforce the structure as required before 
installing the equipment.

Do not begin to install your product until you have read and understood the instructions and warnings contained in 
this installation guide.

Image 1

Image 2

Ceiling Structure

Cable

Anchor

(not provided)

Отзывы: