The following points regarding cabling must be considered:
-
The main contacts of contactors K1 and K2 must be installed between the Fronius
Smart Meter and the inverter and the residual-current circuit breaker of the backup
power circuits.
-
The supply voltage for contactors K1 and K2 is provided by the public grid and must
be connected to phase 1 (L1) after the Fronius Smart Meter and fused accordingly.
-
An NC contact for the relay K3 interrupts the supply voltage to contactors K1 and
K2. This prevents the backup power network of the inverter from being switched to
the public grid.
-
The NO contact of relay K3 gives feedback to the inverter on whether the locking
was successfully performed by relay K3.
-
Additional inverters or other AC sources can be installed in the backup power circuit
after the main contacts of K1 and K2. The sources are not synchronised to the net-
work of the inverter because this backup power network has a frequency of 53 Hz.
-
The use of contactor K2 is optional in Australia.
All-pin separation
cabling variant,
e.g. Germany,
France
Circuit Diagram
The Circuit Diagram can be found in the appendix to this document on
page XX
.
Cabling of backup power circuit and non-backup power circuits
If not all the loads in the home need to be supplied in a backup power situation, the cir-
cuits need to be divided into backup power circuits and non-backup power circuits. The
total load of the backup power circuits must not exceed the nominal output of the
inverter.
The backup power circuits and non-backup power circuits must be fused separately
according to the required safety measures (residual-current circuit breaker, automatic cir-
cuit breaker, etc.).
In backup power mode, only the backup power circuits are disconnected at all pins from
the grid by contactors K1 and K2; a ground connection is only established for these cir-
cuits. The rest of the home network is not supplied with power in this case.
The following points regarding cabling must be considered:
-
The main contacts of contactors K1 and K2 must be installed between the Fronius
Smart Meter and the residual-current circuit breaker of the inverter and the residual-
current circuit breaker of the backup power circuits.
-
The supply voltage for contactors K1 and K2 is provided by the public grid and must
be connected to phase 1 (L1) after the Fronius Smart Meter and fused accordingly.
-
To ensure residual-current circuit breakers function in backup power mode, the con-
nection between the neutral conductor and the ground conductor must be estab-
lished as close as possible to the inverter, but in any case before the first residual-
current circuit breaker. An NC contact is used for this purpose for each of the main
contacts of contactors K4 and K5. This ensures that the ground connection is estab-
lished as soon as the public grid connection is no longer available.
-
As with contactor K1, the supply voltage for contactors K4 and K5 is provided via
phase 1 (L1) of the public grid.
-
An NC contact for the relay K3 interrupts the supply voltage to contactors K1, K2, K4
and K5. This prevents the ground connection from being immediately disconnected
again when power returns to the public grid and the backup power network of the
inverter from being switched to the public grid.
-
The NO contact of relay K3 gives feedback to the inverter on whether the locking
was successfully performed by relay K3.
-
The use of contactor K2 is optional in France.
-
Additional inverters or other AC sources can be installed in the backup power circuit
after the main contacts of K1 and K2. The sources are not synchronised to the net-
work of the inverter because this backup power network has a frequency of 53 Hz.
71
EN
Содержание Symo GEN24 10.0
Страница 2: ......
Страница 10: ...10 ...
Страница 11: ...General information 11 ...
Страница 12: ...12 ...
Страница 28: ...28 ...
Страница 29: ...Backup power variant PV Point OP 29 ...
Страница 30: ...30 ...
Страница 32: ...32 ...
Страница 33: ...Backup power variant Full Backup 33 ...
Страница 34: ...34 ...
Страница 41: ...Installation 41 ...
Страница 42: ...42 ...
Страница 82: ...82 ...
Страница 83: ...Settings web interface of the inverter 83 ...
Страница 84: ...84 ...
Страница 104: ...104 ...
Страница 105: ...Appendix 105 ...
Страница 106: ...106 ...
Страница 116: ...116 ...
Страница 117: ...Circuit diagrams 117 ...