4.4.3 Bulk chute outside
When installing the vertical screw inside the fuel store, remember that the associated
geared motor must be explosion-protected. A horizontal screw extension is generally
required for the wall duct. It must also be ensured that the discharge system in the fuel
store does not collide with the bunker filling system!
4.4.4 Bulk chute recessed in shaft
Alternatively, the bulk chute can be recessed in a shaft. Here the built-in bulk chute is
used instead of the standard bulk chute. During planning additional design information
should be noted in this case.
⇨ See "Installation with recessed bulk chute" [page 29]
Assembly
4
Installation variants - BFSV
Installation- and Operating Intructions BFSV / BFSU | M1420116_en