4.3.2 Installation with mobile bulk chute
5
6
1
With all assembly variants of the BFSV the vertical screw is secured to the wall of the
fuel store with clips and sections. The bracket of the vertical screw is additionally
affixed to the floor with heavy duty anchors. Both the brickwork and the floor must
have sufficient load capacity.
2
The ground around the mobile bulk chute and the access area for the loading vehicle
must be even and also have sufficient load capacity.
3
The control cabinet must be installed within the protected area
4
During operation of the system the operator must be stationed at all times within view
of the bulk chute to be able to respond immediately to any risks which might occur. In
the work area guard structures should be used to ensure that falling wood chips or
moving platform gates of the dumper do not injure the operator. The necessary
protective structures should be dimensioned according to EN ISO 13857.
5
16 pin socket (for layout see circuit diagram included in control cabinet)
6
A 16 pin cable as a connection line between the control cabinet and socket must be
provided by the customer.
4
Assembly
Installation site
28