INSTALLATION CHECK LIST
Blast chiller installation checklist
rev0 of 17/11/2017
Customer name
Installation date
Address
Installer technician
City
Installer company
Country
Model
Tel. no.
Serial number
E-mail address
Supply voltage
Reference contact
Checks
Notes
Check the package status and integrity
Check for aesthetic defects
Remove the protective film from all surfaces
Chiller installed on castors?
YES □
NO □
Condensing unit on the machine?
YES □
NO □
Install the spacers at the back of the
equipment
Position the baking tray support according to
the customer needs
Indicate the available space around the chiller:
left side -
minimum 50 (mm)
…………..
right side -
minimum 50 (mm)
…………..
front (mm)
…………..
back -
minimum 50 (mm)
…………..
above (mm)
…………..
Indicate the equipment around the blast chiller (oven/refrigerator/blast chiller/refrigerated
counter/worktable/dishwasher/wall/free/other)
left side
…………………………………………………………………………………………………………………….
right side
…………………………………………………………………………………………………………………….
front
…………………………………………………………………………………………………………………….
back
…………………………………………………………………………………………………………………….
above
…………………………………………………………………………………………………………………….
Level equipment
Connect condensate drain pipe
bowl □
sump □
Electrical connection
Make sure that the power socket is
equipped with a 30mA circuit breaker
Connect the single-phase models to the
power socket via Shuko plug (already
installed)
Connect the three-phase models via electric
plug (not supplied) suitable for the electric
load of the equipment or connect directly to
the main electrical panel
Plug □
Directly on
panel □
Hydraulic connection
Indicate the water inlet pressure (min. 15kPa
–
max. 400kPa)
Pump use (if water pressure below 150kPa)
YES □
NO □
Check for water leaks from the fittings