Installation
The length of the communications wire between the aGate X and the aPbox should not
exceed 328 feet (100 meters).
Unboxing
Step 1
Inspect the packaging for damage.
Step 2
Use a retractable utility knife to cut open the sealing tape of the package box, with the
knife blade shorter than 0.3 inch to avoid damaging the aPbox case.
Step 3
Remove the box contents and check for the following items:
•
One aPbox
•
One mounting template
•
One accessory bag including the following:
i.
Four 1/4
” water
-tight washers
ii.
Ten cable ties
iii.
Two keys
Step 4
Remove the buffer foam and PE bag wrapping the aPbox.
NOTE
•
Save the mounting template for marking the mounting holes.
•
During handling and installation, make sure the aPbox is well