Decommissioning and removal, storage and disposal | 77
FRAKO | Operating Manual | Power Quality Controller – PQC
10 Decommissioning and removal,
storage and disposal
10.1
Decommissioning the PQC
WARNING!
Danger from electricity!
Touching live components at the instrument terminals and connecting
cables can cause serious injury or may even be life-threatening.
– Installation, commissioning and decommissioning of the PQC may only
be carried out by appropriately qualified personnel who have read and
understood the content of this manual.
– Isolate the PQC and the system from the power supply before decom-
missioning it.
– The isolated electrical system must be locked out to prevent its being
inadvertently switched on again.
– It must be verified that none of the terminals are live.
– All live components in the vicinity must be covered to prevent inadvertent
contact
CAUTION!
Danger from heat
The instrument terminals can become hot during operation and could
cause burns.
– After the PQC has been operating, sufficient time must be allowed for the
instrument and its terminals to cool down before work is carried out on
the connections.
ATTENTION!
Risk to equipment!
If the exposed ends of disconnected cables come into contact with each
other, this can result in short-circuits and overloading of the installation
conductors, resulting in damage to equipment.
– All disconnected cables must be individually isolated and insulated, and
measures must be taken to prevent their inadvertent contact with live
components or electrically conducting parts.
1. Current transformers must be short-circuited.
2. Remove all cables from the PQC.
3. Individually isolate and insulate all disconnected cables and take measures to pre-
vent their inadvertent contact with live components or electrically conducting parts.