6 Commissioning
Page 39 of 67
6.2
Requirements for Commissioning
Before commissioning and putting into service, ensure the following requirements:
Flush the piping
Test the pressure of the piping
6.3
Flushing and Pressure Testing of the Piping
Risk of injury due to pressure hazards!
Exceeded operating parameters/limits during pressure testing may cause severe injury or
death.
Never exceed the operating parameters/limits of the Argus Ball Valve as stated on the
nameplate.
1.
Thoroughly remove all dirt and foreign particles from the piping, valves and
fittings.
2.
Test the pressure of the piping to confirm the tightness and strength of the
industrial plant section.
Flushing and pressure testing of the piping are now complete.
6.4
Operating the Argus Ball Valve
The Argus Ball Valve can be operated manually or automatically by an actuator.
There are three operation positions:
Open (the Argus Ball Valve opens by rotating to the left or counterclockwise)
Closed (the Argus Ball Valve closes by rotating to the right or clockwise)
Half-open (not intended for normal operation)
The Argus Ball Valve is open when the flat flanks of a shaft sealing head or the groove of a
square shaft sealing head are parallel to the flow direction.
For safety reasons the position of the Argus Ball Valve is recognizable by the ball
valve wrench.