ROTARY HEAT EXCHANGER
EQRB
INSTALLATION AND MAINTENANCE INSTRUCTIONS
IMPORTANT!
During installation
– Read the instruction manual completely
before installation and commissioning.
– The installation must be carried out by
qualified personnel.
– General conditions and regulations for
the installation and operation of electrical
machinery must be observed.
– Measures to protect against personal in-jury
and damage to the machine must be taken
following local rules and regulations
– The EMX-R drive system is intended for
permanent installation.
– Cables must not be connected or
disconnected while the supply voltage is on.
– Check that the equipment is correctly
connected before it is taken into use.
See the instructions for mounting/
connection.
– Faults that arise due to faulty installation or
operation are not covered by the guarantee.
During operation
– Measurement in the control unit during
operation may only take place at the
connection terminalblocks.
N.B.! Great care must be taken.
– The units may not be opened or
disassembled while they are operating.
Regarding the control logic and operation:
During start up and after each time the AHU
has been stopped, it is recommended that the
exhaust fan operates during 1 minute before the
supply fan is started.
SAFETY INSTRUCTIONS
INSTALLATIONS INSTRUCTION, DRIVE SYSTEM
EMX-R, EQRB SIZE 020-090