4 Commissioning
4.1 Generalities
All electrical supply, operating and measuring lines and the pressure connec-
tions must have been correctly installed before starting operation and the flange
connections must have been correctly made. All supply lines are arranged so
that there are no mechanical forces acting on the device.
NOTICE! Leak test
The leak tightness of the flange connection must be tested in the course of the
system leak tests.
4.2 Function test
There is a test button outside the pressure chamber with which a function check
as per DIN 4754-3 can be made without lowering the fill level. When pressed,
the body of the swimmer is moved against its buoyancy.
The factory default switching point of switch S1 (clamps 1, 2, 3) is set so that it
switches when the swimmer rod is horizontal. The optional warning switch S2
switches ca. 2.5 mm before S1.
Check the function of the unit:
• Check the switching function (with the aid of the test button) in combination
with the following components.
• Check the swimmer via the buoyancy behaviour after pressing the test but-
ton.
If the result of the function test is negative, the fill level limiter must be taken out
of operation and the process must be kept safe by other means.
Содержание NK10 B
Страница 1: ...Operating manual NK10 Fill Level Limiter 09005111 BA_EN_NK10 Rev ST4 E 01 19 09005111 ...
Страница 19: ...FISCHER Mess und Regeltechnik GmbH Attachments 8 BA_EN_NK10 19 28 Fig 13 CE_DE_NK10 part2 ...
Страница 22: ...8 Attachments FISCHER Mess und Regeltechnik GmbH 22 28 BA_EN_NK10 Fig 16 DNVGL_TAA000020S_Page_2 ...
Страница 23: ...FISCHER Mess und Regeltechnik GmbH Attachments 8 BA_EN_NK10 23 28 Fig 17 DNVGL_TAA000020S_Page_3 ...
Страница 27: ...FISCHER Mess und Regeltechnik GmbH Attachments 8 BA_EN_NK10 27 28 Fig 21 SIL_IEC61508_DE_EN 1 Part2 ...