4. Commissioning CPV−CS02 (ABB CS31)
4−6
Festo P.BE−CPV−DI02−EN en 0704NH
4.1.3
General data
A CPI/CP system can be fitted with a different number of in
puts and outputs. The addressing of the CPV Direct is based
on the specifications of the CS31 system bus.
The following applies to the CPI/CP system: 16 inputs or
16outputs each occupy one CS31 bus address. A 16−group
which has been started also occupies a full CS31 bus address.
No
te
Select the range n = 0
Ū
60 for the address to be set in the
CPV Direct. In this way valve terminals and CPI output
modules connected to the CPI extension connection can
then also be addressed.
Note that the CPI system occupies several station numbers
depending on the extension on the CPI connection.
Содержание PROFIBUD-DP
Страница 2: ......
Страница 15: ...Installation CPV DI02 and CPV CS02 1 1 Festo P BE CPV DI02 EN en 0704NH Chapter 1...
Страница 58: ...1 Installation CPV DI02 and CPV CS02 1 44 Festo P BE CPV DI02 EN en 0704NH...
Страница 59: ...Commissioning CPV DI02 PROFIBUS DP 2 1 Festo P BE CPV DI02 EN en 0704NH Chapter 2...
Страница 79: ...Diagnosis CPV DI02 PROFIBUS DP 3 1 Festo P BE CPV DI02 EN en 0704NH Chapter 3...
Страница 107: ...Commissioning CPV CS02 ABB CS31 4 1 Festo P BE CPV DI02 EN en 0704NH Chapter 4...
Страница 116: ...4 Commissioning CPV CS02 ABB CS31 4 10 Festo P BE CPV DI02 EN en 0704NH...
Страница 117: ...Diagnosis CPV CS02 ABB CS31 5 1 Festo P BE CPV DI02 EN en 0704NH Chapter 5...
Страница 131: ...Technical appendix A 1 Festo P BE CPV DI02 EN en 0704NH Appendix A...
Страница 146: ...A Technical appendix A 16 Festo P BE CPV DI02 EN en 0704NH...
Страница 147: ...Index B 1 Festo P BE CPV DI02 EN en 0704NH Appendix B...
Страница 148: ...B Index B 2 Festo P BE CPV DI02 EN en 0704NH Contents B Index B 1...
Страница 154: ...B Index C 8 Festo P BE CPV DI02 EN en 0704NH...