background image

Fig. 5

 

STEP 1:    SOLAR REEL PLACEMENT:

ABOVE-GROUND SOLAR COVER 

REEL SYSTEM

ASSEMBLY INSTRUCTIONS 

PLEASE READ ENTIRE INSTRUCTIONS CAREFULLY BEFORE PROCEEDING

 

 

REEL SYSTEMS COMPONENTS AND PREPARATION:

Tools required for assembly:

·

Portable drill 

·

Tape measure 

·

Pencil and Scissors 

 

 

 

 

A.

B.

 

 

 

 

 

Insert both End Tubes equal distance into Center Tube 
and Mark on Center Tube where inner tubes end.

 

Fig. 3

STEP 2:  TUBE ASSEMBLY  

for L18, L18M*, L24M* (mill*) Tubeset

B.

                                                        

C.

 

D.

                                                                                               

 

E.

 

 

 

C3

 

 

C2

 

 

End tube

End tube

Center tube

C1

C1

Fig. 4

A.

Ends & Hardware Parts List:         

2 Ends (Tees)

2 Cones

2 Handles

2 Bearings

2 Plugs for “L” Series Tubesets

10 Strap Plates

10 - 26” Straps

Hardware Kit: 

10 Plastic Screws
4 Wing nuts & bolts
25 Metal Self-
Drilling Screws

Leave an extra 4“ (10 cm) on cover length if installing at mid-point or widest point to allow for fold (see Fig. 1)   

 Trim cover to clear inside top edge of pool. 

 Cover should not touch sides of the pool when rolling up .

Lift off and Swing”

Removal Feature

Fig. 1

Carefully measure between inside flat edges of two cones to calculate overall length for the tubes. 

 Use Minimum Insertion Table below. 

Measure between inside 

flat edges of 2 cones.

Pool

Fig. 2

Lock tubes together by rotating the center tube in the opposite direction to end tube.  HOLD TUBES LOCKED WHILE YOU 
INSTALL FIRST SELF-DRILLING SCREW ON A DRILL LINE, 1“ (2.5 cm) back from end of center tube at location ”C1” (Fig. 4 & 5).
If necessary, a very small “pilot hole” may be drilled. 

Place 2 more self-drilling screws at Location “C2” and ”C3” - 1 screw on every second
Drill Line around tubes (see Fig. 4).

At “D” locations, install 3 screws around the center tube on every second drill line, 1“ (2.5 cm)
back from where you marked the end of the inner tube (see Fig. 4).

Repeat for other end tube.
    

Tubes Must be in locked position then install first screw.
Drill Lines DO NOT line up when tubes are properly locked

PREMIUM (FG7B)

D3

D2

D1

End Tube

Center Tube

End Tube

1/4“ Drill Bit

·

D1

First determine the potential placement of the post cones.  

Cones must be Level

 and on outer 

side of top rail.  Ensure adequate space under the rail to tighten the wing nuts (see Fig. 2)  Cones 
will be attached after reel system has been assembled.

Getting started:    

  

Safety Glasses recommended

line up when tubes 
are properly locked

Drill lines MUST NOT

Four Easy Steps:  

   

  

         

If you need additional assistance, contact us at [email protected] or call 905-876-4766 Monday to Friday 8:30 a.m. to 5:00 p.m. Eastern Time. 

 

 

 

 

Weight

Tube 

 Min.        Max.            Max. Wet 

    Max.

L18/L18M* 9“

  18’6“ (5.7 m) 

60# (27.3kg)  18’x36’

 

Insert      Width 

 Cover 

  Cover

(3 tube Configuration)

L24M*

 

  

13“

  24’6” (7.3 m) 

50# (22.7kg)        24’ 

On round pools, the reel should be located across the center of pool or slightly off center with cover
extensions folded in (see Fig.1). On oval or rectangular pools, locate the reel across widest point. 

* Mill tubes tarnish over time.  Anodized tubes help reduce tarnishing.

THIS STEP REQUIRES 6 SELF-DRILLING stainless steel screws at EACH TUBE JOIN. 

 

DO NOT pre-drill holes or over-tighten screws. 

A very small “pilot hole” is acceptable. 

Tube Join

C1

D1