HYDRAULIC SYSTEM
070002_3_B
FGP 50/2 EVO-2
9
HYDRAULIC SYSTEM
HYDRAULIC SYSTEM LAYOUT
1ST PHASE - PRE-WASHING:
At the burner starting, the light-oil, sucked by the pump (pos.2), is cleaned by the filter (pos.1) and sent to the return
pipe through the by pass regulator (pos.3).
2ND PHASE - 1ST STAGE IGNITION:
After about 15secs. of pre-washing, the valve V1 opens, the light-oil comes out atomized by the nozzle (1ST) and it is
ignited by the voltaic arc generated by the ignition transformer. The pump light-oil excess delivery is by-passed on the
return pipe through the pressure regulator (pos.3).
SAFETY TIME:
After about 5-10 secs. from excitation of the 1st stage valve V1, if the light-oil does not ignite, the burner stops (lock).
3RD PHASE - 2ND STAGE IGNITION:
After about 5-10 secs. from the igniton of the 1st stage, the 2nd stage valve V2 gets excited and the light-oil is sent to
the 2nd nozzle (2ND) and at the same time to the jack (pos.4) which causes the opening of the 2nd stage air shutter.
ELECTRICAL SYSTEM
ELECTRICAL PANEL LAYOUT
Please refer to elctrical panel layout supplied with the present Instructions.
WORKING DIAGRAM OF THE ELECTRICAL DEVICE
Please refer to electrical device handbook supplied with the present Instructions.
Fig. 9
Hydraulic system layout