8.3.1 Machine unfolding procedure
Machine unfolding procedure – work position
Initial position: The machine is lifted on the axle, the side frames are secured with hooks, both external
ball valves are closed, and the three-way valves are in the position for hook control.
1
Open the stop valve of the red
circuit. Unlock the side frames
by lifting the hooks up.
2
Rearrange
the
three-way
valves.
Unfold the machine using the
red circuit.
3
Draw out the piston-rods of
the side rollers using the
yellow circuit into the marginal
position, i.e. maximum release.
Draw in the piston-rods of the
axle using the green circuit into
the marginal position, i. e.
maximum
insertion.
The
machine will rest on all rollers
equally.
Place the relevant number of
spacer rings on the roller
piston-rods and set the tracing
wheel
(according
to
the
required
recess
of
the
machine). If the machine is
equipped with a drawbar for
fixed suspension, set the
distance washers also on the
drawbar piston rods. Draw in
the piston-rods of all rollers
(drawbar) using the yellow
circuit. The machine is ready
for work.
28
|
50
Содержание SOFTER 9 PSW
Страница 2: ...2 50 Prepared by Technical Department Farmet a s on 3 5 2022 changes reserved...
Страница 4: ...PREFACE 4 50 IMPORTANT READ CAREFULLY BEFORE USE KEEP FOR FUTURE REFERENCE...
Страница 6: ...PREFACE 6 50...
Страница 15: ...WORK SAFETY LABELS Fig 1 Location of safety labels on the machine SOFTER 9 PSW 15 50...
Страница 16: ...WORK SAFETY LABELS SOFTER 12 PSW 16 50...
Страница 27: ...COMMISSIONING Machine position for unfolding 27 50...
Страница 50: ...SERVICING AND WARRANTY CONDITIONS 50 50...