MACHINE UNFOLDING PROCEDURE
Tab. 5 – Work position of the machine
Machine Unfolding Procedure – Work Position
Initial condition: The machine is lifted on the axle (height up to 4 m), the side frames are secured with hooks, the
spherical valves closed for transport, the switching valve is set to securing hooks.
1
Switch both levers of the green circuit to
the right (open).
Lift the machine up to the maximum
height using the green circuit.
Using the red circuit, release the securing
hooks of the side frames.
2
Switch the lever of the folding circuit to
the left (red circuit, for frame folding).
Unfold the side frames with the red
circuit. On the manometer, set the side
frame downforce to 100 bar.
Lift the axle with the yellow circuit up to
the working position.
Place the corresponding number of washers on the piston rods of the rollers and the tow bar, check the
copying wheel depth setting pin position and set the side leveling discs to the working position.
The machine is ready for work. Headland turning is performed using the green circuit.
SETTING THE DOWN PRESSURE OF SIDE FRAMES
When the machine has been unfolded, the down pressure of the side frames must be
adjusted to ensure optimal terrain tracing.
Set the value of
100 bar
on the pressure gauge using the circuit for unfolding.