7.  Commissioning 

 

Initial Commissioning

.  

 

Refer to the General Arrangement (GA) drawing for the Air Supply Isolator systems operating layout. 
 
If, after commissioning, the system does not perform as expected, refer to the Fault Finding Section. 
 
Follow these steps: 

1.  Disconnect the air supply pipe from the inlet to the Air Isolation unit system. 
2.  Flush the pipe through with instrument quality air to remove any debris. This must be carried out for at 

least 10 seconds for every metre of supply pipe. 

3.  Check all connections between the system and the downstream motor purge unit. 
4.  Close and re-open the internal valves. See No. 3 and 6 in the GA drawing. 

8.  Maintenance of the System 

 
The maintenance recommended for the system consists of the following, supplemented by any additional local 
requirements imposed by the local Code of Practice. 

 

Expo recommends that the commissioning tests be repeated at every six to 24 months, dependent on the 
environment. In addition the following checks are also recommended at that time: 

  Check the condition of the air supply filter element. Clean or replace it as necessary. 

 
At least every two years, the following additional checks are recommended: 

  Apparatus is suitable for the Hazardous Location 

  There are no unauthorized modifications 

  The source of air is uncontaminated 

  Approval labels are legible and undamaged 

  Adequate spares are carried 

 

9.  Fault Finding 

 

If the system does not behave in the manner described above there is a fault.  Some of the more likely faults 
are dealt with below. If a cure cannot be affected by following the procedure shown below please call Expo (24 
hour answering) or your supplier for further assistance. 
 
Check components by substitution only after establishing that such action is necessary. If the system is less 
than 12 months old, parts under warranty should be returned to Expo for investigation, with a full report of the 
fault and the system Serial Number. 
 
As with any pneumatic system the greatest enemies are water, oil and dirt in the air supply. For this reason the 
air system must always incorporate a dust and water filter to provide air to instrument quality. 

 

10.  Recommended Spares List 

 
KFL-A01N-001  

 

 

 

 

Filter kit for S0015/275 filter/regulator 

 

11.  Drawings and Diagrams 

 
The following drawings are attached:  
Title   

 

 

 

 

Drawing Number    

 

Sheet(s) 

  

Air Isolation Unit 2”   

 

 

ASU-0000-009-GA 

 

1 of 2 & 2 of 2 

 

Содержание ML576

Страница 1: ...s apply only to the Pressurizing system It is the responsibility of the manufacturer of the Pressurized Motor Enclosure to provide appropriate instructions for the Enclosure Contents 1 ASU 0000 009 Ge...

Страница 2: ......

Страница 3: ...installed by a competent engineer in accordance with relevant standards and any local codes or practice Ensure the system is installed according to the full instructions in the Installation of the Sys...

Страница 4: ...both small two way valves located at the bottom of each filter should be normally closed 5 Main Components Air Supply Filter The unit is provided with x2 40 liquid dust filter elements The user of th...

Страница 5: ...r isolation unit system an external shut off valve with the same or larger thread size as the Control Unit inlet fitting should be fitted by the installer to prevent any restriction of purge flow The...

Страница 6: ...llowing checks are also recommended at that time Check the condition of the air supply filter element Clean or replace it as necessary At least every two years the following additional checks are reco...

Страница 7: ...re Copyright Expo Technologies Limited They are to be treated as confidential and are returnable upon request They are not to be copied or communicated in part or in whole without written consent from...

Страница 8: ...KET 1 23 S0015 018 PRESURE GAUGE 2 24 HTS A200 803 2 S STEEL PIPE THREAD BOTH ENDS 1 25 RLCI 04025 J NUTSERT CLOSED M4 9 26 HF1 A01N 006 2 INCH FILTER 2 27 TPE 106M 0P0 STUD ELBOW 1 8 BSPT x 6 OD PUSH...

Страница 9: ...This Page Intentionally Left Blank...

Страница 10: ...This Page Intentionally Left Blank...

Страница 11: ...This Page Intentionally Left Blank...

Страница 12: ...Technologies UK Expo Technologies Ltd Unit 2 The Summit Hanworth Road Sunbury On Thames TW16 5DB UK T 44 20 8398 8011 F 44 20 8398 8014 E sales expoworldwide com Expo Technologies China Qingdao Expo...

Отзывы: