background image

Louvre Assembly Instruction

  

For the louvre assembly you will need 1 top cill, 1 bottom 
cill, 2 side jambs(one with handle), 4 self tapping screws, 
4 crop head bolts and nuts and glass blades or polycar-
bonate blades (including  4 alu.clips and 2 PVC anti-dust 
strip).

  

2.  Installation of louvre to the structure 

* 

The louvre is fitted after the unit is assembled fully and during glazing. 

* 

The louvre is fitted to the vertical glazing bar/wall or corner bar utilizing either 4 unoccupied bolts previ-
ously inserted, or the 4 crop head bolts supplied with the louvre kit. 

* 

The louvre is fitted from inside the structure with the angle jams fitting around the vertical greenhouse 
bars concerned. 

* 

The louvre handle is on the inside of the greenhouse and is fitted to the right of the louvre ( as viewed 
from the inside) 

* 

First you should locate where to fit the louvre, To determine the height, place the relevant piece of poly-
carbonate panel below the louvre position. this position will vary . 

* 

Then you should cut polycarbonate panel, If you want to fit the louvre in the middle of of polycarbonate 
panel, then cut size 456mm (remove middle part size 456mm) and remain both ends.  If you want to fit 
louvre at the end of panel, then cut 475mm size from PC panel end (remove end part). 

Procedure

 

1.  Installation of Louvre frame 

* 

Place top cill into position on side jamb of louvre and secure with self tapping screws. 

* 

Do same on the other top corner. 

* 

Do same with bottom cill. 

* 

Please note that the handle is on the right hand side. The diagrams are viewed from inside. 

* 

You attach the louvre to the frame during the glazing of the greenhouse. 

 

475

 

456

 

Отзывы: