Initial Commissioning Procedure
The following will be checked when commissioning the unit. The method may vary depending on the
project.
Evinox Energy Commissioning Check-List
1
Check if the unit is connected correctly to the hydraulic circuits. Confirm that the
unit is correctly connected to the electrical supply.
2
Set the unit into operation by installing firmware, checking if all the components are
functional.
3
Confirm the unit performs cooling function. If Evinox ViewSmart Room Controller is
used this will include ViewSmart functionality check.
4
Ensure the unit has an ID number, record serial numbers of the control board and
the heat meter.
Evinox Technical Personnel
Evinox Technical Personnel who will visit the project during the course of the
installation and at completion to arrange for final commissioning and calibration,
do so to assist the contractor and install team to deal with any questions and
queries. They do not perform the role of quality control or inspector of the
installation or provide approval for the works carried out.
Booking Commissioning
All commissioning must be booked 6 weeks in advance and will be carried out to a
pre-agreed programme that will be confirmed with the client prior to
commissioning.
Warranty
Evinox Energy Commissioning is required for warranty validation.