SPH/SPC SERVICING AND INSPECTION 

SPH/SPC inspection should be carried out every 2 years in line with the current regulations, 
standards and guidelines. Which is, but not limited to BSRIA Heat Interface Unit Guide BG62/2015 

 

 

Evinox Energy ModuSat SPH/SPC Servicing and Inspection Checklist

 

Check 

No leaks associated with SPH/SPC 

 

Visual inspection of primary isolation valves  

 

Strainer valves clean where accessible  

 

Primary differential pressure above required minimum  

 

Thermal insulation intact 

 

Secondary heating/cooling system pressure within nominal range 

 

Control valves respond to demand for heating/cooling 

 

Heating/Cooling pump is functional 

 

Primary supply temperature as commissioned 

 

10  Heat meter registers demand 

 

11  Appliance can be read remotely (where applicable) 

 

12  Consumer satisfied with heating/cooling performance 

 

13  Take primary water sample  

 

 

 

 

 

 

 

 

 

 

 

Содержание ModuSat SP Cooling Unit

Страница 1: ...2551988D ModuSat SP Cooling Unit ModuSat SP Heating Unit Installation Manual...

Страница 2: ...NERAL INFORMATION 1 TECHNICAL FEATURES 3 INSTALLATION 7 Water treatment 13 Electrical Connections 15 5 2 1 RJ45 Connections 16 SETTING INTO OPERATION COMISSIONING 19 6 3 1 Pressure independent control...

Страница 3: ...2551988D SPH SPC SERVICING AND INSPECTION 23 WARRANTY 24 KIWA CERTIFICATE 26...

Страница 4: ...nd operating the ModuSat unit Failure to read and follow the instructions provided within this document may cause a safety hazard or and failure of the equipment Qualified personnel only The Evinox co...

Страница 5: ...rks on the unit Qualified personnel Electrical installation must only be carried out by technical personnel In the case of water leak Slowly close the isolation valve at the top of the unit Contact Ev...

Страница 6: ...er flow is used to produce secondary heating cooling Apartment heating cooling when the space heating cooling demand is requested by the end user controller the heating cooling operation is started Th...

Страница 7: ...r 2 Pressure Independent Control Valve PICV with actuator 3 Heat meter Cooling Secondary Side Circuit 4 Expansion vessel 5 Low pressure switch 6 Safety relief discharge 7 Pressure gauge 8 Dwelling cir...

Страница 8: ...Water Primary circuit max pressure 16 bar Optional Primary minimum differential pressure 50 kPa 0 5 bar may vary depending on the required output Primary maximum differential pressure 400 kPa 4 bar m...

Страница 9: ...r access and servicing Top 190 mm should be allowed for the flushing bypass kit on the top of the unit with 3 4 connections and 250 mm for the units with 1 connections Front 700 mm Side 50 mm Bottom S...

Страница 10: ...tion site or the property Lifting Take care when lifting this appliance It is recommended that at least two people perform the lifting Leave caps over the connections Ensure that the protective cover...

Страница 11: ...ed to be wall mounted with the typical primary and secondary connections as shown below The Evinox Energy flushing by pass valve kit should be installed prior to connecting the unit and the valves lef...

Страница 12: ...ng the ModuSat SPC Pre Installation Rig on the wall fixing bracket Then slide down by 15mm and across to the right by 30mm as indicated in diagram STEP2 Fit the Evinox Energy Flushing Bypass Valve Kit...

Страница 13: ...ystem The kit includes an H shape by pass with inbuilt isolation valve 1 strainer and 3 isolation valves Evinox FLUSH KIT C01 SS for ModuSat SPC Evinox FLUSH KIT SP1 SS for ModuSat SPH Close valves Be...

Страница 14: ...ting the ModuSat heat interface unit ensure that all the connections are tightened to avoid any leaks First fill of the HIU Clean and flush the system before connecting the unit Filling the system sho...

Страница 15: ...ating or cooling system The ModuSat unit is fitted with a manometer gauge that is mounted in the front panel This gauge reading should be used when filling the secondary circuit An external filling lo...

Страница 16: ...to BSRIA Application Guide BG29 2012 BS7593 2006 Requirements of Thames Water Utilities The Water Industry Act 1991 Section 119 HSE The Control of Legionellosis 1991 HSC Approved Code of Practice and...

Страница 17: ...t consultants that the chemicals used and cleaning method statement complies with the requirements set out in this section Evinox Energy do not take responsibility for approving inhibitors used for do...

Страница 18: ...anty Evinox Energy cannot accept any responsibility for incorrect wiring The ModuSat wiring board is located within the ModuSat itself under a removable metal cover To access the connection board the...

Страница 19: ...ol board is located next to the connection board on your right hand side The control board cover must not be removed Doing so may invalidate the warranty Connection Terminations Evinox Energy strongly...

Страница 20: ...17 2551988C ModuSat Connection Board Please Note When connecting external valves or pumps to the ModuSat control board it must be ensured that each connection does not exceed 1amp 220 240V AC...

Страница 21: ...ING WITH NOTES AT THE END OF THIS MANUAL SmartTalk system wiring Typical Modbus system architecture SEE STD MOD 2013 BUS 1 E DRAWING WITH NOTES AT THE END OF THIS MANUAL Typical TCP IP system architec...

Страница 22: ...ort to Evinox Energy Pre commissioning checklist Pre requisite of Commissioning Check 1 Primary network and plant room fully operational and complete including water treatment in line with these instr...

Страница 23: ...nction will run for a pre set period of approximately 45minutes Rocker Switch Please note The rocker switch below the commissioning push button is the Pump Manual Override This should NOT be operated...

Страница 24: ...ks red green Pump in function but stopped Pump restarts by itself after the fault is disappeared 1 Low voltage U 160 V or High voltage 253 V 1 Check voltage supply 195 V U 253 V 2 Module overheating t...

Страница 25: ...k 4 Ensure the unit has an ID number record serial numbers of the control board and the heat meter Evinox Technical Personnel Evinox Technical Personnel who will visit the project during the course of...

Страница 26: ...Visual inspection of primary isolation valves 3 Strainer valves clean where accessible 4 Primary differential pressure above required minimum 5 Thermal insulation intact 6 Secondary heating cooling s...

Страница 27: ...strictly limited to the supply free of charge of parts acknowledged as being defective after inspection by our technical department Any costs arising from this inspection will be charged if the part...

Страница 28: ...installation and servicing manuals to ensure long life reliability and efficiency Exclusions to the Warranty The following are not covered by the warranty Electric degradation of parts resulting from...

Страница 29: ...26 2551988C KIWA CERTIFICATE...

Страница 30: ...G PRODUCT DEVELOPMENT NOTES TYPICAL WIRING CONNECTION ARRANGEMENT WITH TWO ROOM CONTROLLERS AK SEP 2018 N T S PL STD MOD BMS Electric wiring of MODUSAT and VIEWSMART The MODUSAT connection board is in...

Страница 31: ...ACTERISTICS OF ITS EQUIPMENT WITHOUT PRIOR NOTICE AS PART OF ITS CONTINUING PRODUCT DEVELOPMENT NOTES Energy MODUSAT SmartTalk DATA LOGGER AND SUPPLY UNIT BUS PRINCIPLE SYSTEM ARCHITECTURE BJW AUGUST...

Страница 32: ...TIONAL NETWORK SWITCH INSIDE APARTMENT OPTIONAL MODUSAT UNIT MODUSAT CONTROL BOARD MODUSAT UNIT MODUSAT CONTROL BOARD MODUSAT UNIT MODUSAT CONTROL BOARD MODUSAT UNIT MODUSAT CONTROL BOARD NETWORK SWIT...

Отзывы: