SPH/SPC SERVICING AND INSPECTION
SPH/SPC inspection should be carried out every 2 years in line with the current regulations,
standards and guidelines. Which is, but not limited to BSRIA Heat Interface Unit Guide BG62/2015
Evinox Energy ModuSat SPH/SPC Servicing and Inspection Checklist
Check
1
No leaks associated with SPH/SPC
2
Visual inspection of primary isolation valves
3
Strainer valves clean where accessible
4
Primary differential pressure above required minimum
5
Thermal insulation intact
6
Secondary heating/cooling system pressure within nominal range
7
Control valves respond to demand for heating/cooling
8
Heating/Cooling pump is functional
9
Primary supply temperature as commissioned
10 Heat meter registers demand
11 Appliance can be read remotely (where applicable)
12 Consumer satisfied with heating/cooling performance
13 Take primary water sample