PREPARATION

A )  Download the Enphase Installer Toolkit mobile app and 

open it to log in to your Enlighten account. With this app, 

you can connect to the IQ Envoy to track system installa-

tion progress. To download, go to 

enphase.com/toolkit

 or 

scan the QR code at right.

B)  Check the box for the following items:

• 

Enphase IQ C with IQ Envoy

• 

Enphase IQ C Quick Install Guide

 (this document)

C )  Make sure you have the following 

required

 items:

• 

Tools: screwdriver, pliers, and torque wrench.

• 

Up to four Eaton BR-style breakers (one for each DG branch circuit).

• 

Overcurrent protection in the load center in accordance with NFPA 

70, §705.12.

• 

Suitable mounting hardware: use #8 (or larger) screws that are long 

enough to secure the unit to the vertical mounting surface

• 

Copper conductors rated for wet locations and sized to meet local 

code requirements and voltage drop/rise considerations. Wire sizes 

and torque values are listed on the door of the unit.

• 

UL Listed rain-tight hubs for wire entry into the enclosure.

D )  If you plan to do consumption metering:

• 

Make sure you have two split-core consumption metering CTs (order 

CT-200-SPLIT).

• 

Check that there is enough space in the load center to install CTs. 

Do not install the CTs in a panel where they exceed 75% of the wiring 

space of any cross-sectional area within the load center.

E )  Decide how to connect the IQ Envoy to the Internet: Use Wi-Fi, an En-

phase Mobile Connect modem, or Ethernet. Then, make sure you have 

the following optional items, if needed:

• 

Enphase Mobile Connect modem 

• 

Ethernet over power line communication (PLC) bridge with Ethernet 

cables (order EPLC-01)

• 

Ethernet cable: 802.3, Cat5E or Cat6, unshielded twisted pair (UTP). 

Do not use shielded twisted pair (STP) cable. You must install a 

ferrite bead (we recommend Fair-Rite 0431167281) as close as 

possible to the IQ Envoy on the Ethernet cable.

F )   Create a paper installation map to record device serial numbers and 

positions in the array. You will scan this map later using Installer Tool-

kit and your mobile device.

• 

Write the IQ Envoy serial number on the paper installation map. Later, 

you will need to enter this number in Installer Toolkit. You can type it 

in manually or scan the label on the inside of the Combiner door.

• 

Always keep a copy of the installation map for your records.

H )  

Note that installation of the Combiner has two parts.  

To ensure successful device detection, complete Part 2 after install-

ing any Enphase IQ Microinverters and/or Enphase AC Battery(ies).

Note

:

 If needed, you can find an installation map at the back of any 

Enphase Microinverter Quick Install Guide.

(Model X-IQ-AM1-240-2)

IQ Envoy Display and Controls

Network Communications LED 

Green when IQ Envoy is connected  

to Enlighten.

AP Mode LED

Green when IQ Envoy’s AP Wi-Fi  

network is available.

AP Mode Button

Press to enable IQ Envoy’s AP Mode  

for connecting with a mobile device.  

Hold for 5 seconds to start WPS  

connection to a router. 

Power Production LED 

Green when microinverters are  

producing power.

Device Communications LED

Green when devices are  

communicating with IQ Envoy.

Device Scan Button

Press to start/stop 15 minute scan for  

devices over the power line.

Track system installation progress with the Enphase Installer Toolkit mobile app. 

The LEDs on the IQ Envoy are solid green when a function is enabled or performing  

as expected, flashing when an operation is in progress, or solid amber when  

troubleshooting with Installer Toolkit is required. For a legend of all LED states,  

see Troubleshooting

a

.

Enphase Installer 

Toolkit mobile app

How It Works

POWER LINE  

COMMUNICATIONS

NETWORK  

COMMUNICATIONS

IQ Series  

Microinverters

IQ C  

and IQ Envoy

Load

Center

Router

Enphase 

Enlighten™

To Internet

Installing the 

Enphase IQ C

The Enphase IQ C™ combines up to four AC branch circuits of Enphase IQ Series Microinverters and/or Enphase IQ Batteries. To install the IQ C, 

read and follow all warnings and instructions in this guide. Safety warnings are listed on the back of this guide. If you do not fully understand any of the concepts, 

terminology, or hazards outlined in these instructions, refer installation to a qualified electrician or installer. These instructions are not meant to be a complete 

explanation of a renewable energy system. All installations must comply with national and local electrical codes. Professional installation is recommended.
The IQ C is an outdoor-rated, NRTL-certified NEMA type 3R, polycarbonate enclosure containing an Enphase IQ Envoy™, circuit breaker, and wiring for 

IQ Envoy connections. 

IMPORTANT: 

Enphase IQ Series Microinverters require the Q Cable and are not compatible with previous Enphase cabling. An IQ Envoy is required to moni-

tor performance of the IQ Microinverters

The Q Accessories work only with Enphase IQ Series Microinverters.

Enphase Batteries

Содержание IQ Combiner+

Страница 1: ... that installation of the Combiner has two parts To ensure successful device detection complete Part 2 after install ing any Enphase IQ Microinverters and or Enphase AC Battery ies Note If needed you can find an installation map at the back of any Enphase Microinverter Quick Install Guide Model X IQ AM1 240 2 IQ Envoy Display and Controls Network Communications LED Green when IQ Envoy is connected...

Страница 2: ... sized to meet local code requirements and voltage drop rise considerations B Bring in the wires from each AC branch circuit C Connect the ground green or green yellow to the ground busbar D Pass the L1 conductors from each PV branch circuit through the produc tion CT in the same direction as the arrow on the side of the CT E If you use the fourth Battery PV breaker position for PV you must route ...

Страница 3: ...nstall consumption metering CTs DANGER Risk of electrocution Do not install CTs when cur rent is flowing in the sensed circuit Always install CT wires in the terminal blocks before energizing the sensed circuit Load Center To Grid From IQ Combiner IQ Envoy Terminal Block Relay contacts if needed UP TO 250 Vac 100A 0 5V 45 66Hz white blue Not used white blue P1 C1 C2 1 2 3 4 NO Ref Common C Digital...

Страница 4: ...file settings 8 INSTALLATION Part 2 You must complete Installation Part 2 after installing any Enphase IQ Microinverters and or Enphase Battery ies Detect Devices A Turn on the DG breaker s B Use one of the following methods to detect devices Enphase IQ Microin verters and or Enphase Batteries Method A Provision devices with Installer Toolkit Use the Installer Toolkit mobile app to configure the I...

Страница 5: ...Toolkit mobile app to see which devices are not com municating Check that the circuit breaker s in the IQ Combiner for the PV array are in the ON position Verify that the PV modules are connected to the microinverters Verify the PV module DC voltage is within the allowable range for the microinverter c Power production issues If the Power Production LED lights solid amber check the Installer Toolk...

Страница 6: ...eded WARNING Before installing or using the IQ Combiner read all instruc tions and cautionary markings in the technical description and on the equipment WARNING Use the circuit breakers in the Enphase IQ Combiner only for serving Enphase equipment No other loads are allowed FCC Statement This equipment has been tested and found to comply with the limits for a Class B digital device pursuant to par...

Отзывы: