background image

  Q U I C K

  I N S T A L L  

G U I D E

 

(Models ENCHARGE-3T-1P-INT and ENCHARGE-10T-1P-INT)

Install the Enphase 

Encharge Storage System

To install the Enphase

 

Encharge 3T

™ storage system or 

Encharge 10T

™ storage system and the Enphase wall-mount bracket, read and follow all warnings and 

instructions in this guide. Safety warnings are listed on the back of this guide. These instructions are not meant to be a complete explanation of how to design 

and install an energy storage system. All installations must comply with national and local electrical codes and standards. 

Only qualified electricians shall 

install, troubleshoot, or replace the Encharge 3T or Encharge 10T.
The Encharge

 storage system includes the Enphase Encharge Battery(ies) with integrated Enphase IQ

™ 

Microinverters. The Enphase Envoy™ communica

-

tion gateway measures PV production and home energy consumption. The Encharge storage system senses when it is optimal to charge or discharge the 

battery so that energy is stored when it is abundant and used when scarce. 

Unique installation scenario is shown below:

© 2021 Enphase Energy. All rights reserved. Enphase, the Enphase logo, Encharge storage system, Envoy, IQ microinverter, Installer Toolkit, Enlighten and 

other trademarks or service names are trademarks of Enphase Energy, Inc. Data subject to change. Rev 04 - 07-20-2021

Self consumption, grid tied. 

                              

The preferred configuration when

adding battery storage and PV for self

consumption in a grid-tied application with 

no option for backup during outages. PV 

and Encharge will not operate when the 

grid is unavailable.

PREPARATION

A )  Inspect the packaging and the Encharge Battery(ies) for damage, such 

as cracks, dents, or leaking electrolyte. 

Do not install or use the Encharge 

Battery(ies) if it has been damaged in any way

. If damaged, contact your 

distributor for replacement.

B )  Ensure that your kit includes the following Encharge components:

• 

The 

Encharge 10T

 includes three batteries and two interconnect cable 

assemblies, an Encharge 10T triple-width cover, and a triple-width 

mounting bracket.

• 

The 

Encharge 3T

 includes one battery, and single-width cover with a 

single-width mounting bracket. 

NOTE

: Check the “Energize By” label on the shipping box to verify that 

the Encharge Battery(ies) will be installed by the date shown. If the date 

has passed, contact your distributor for next steps.

WARNING

: Risk of injury. Take care when lifting. The Encharge 

Battery unit is heavy (40.5 kg) and requires two persons to lift.

C )  Ensure you have the following 

required Enphase items

:

• 

The Enphase Encharge system requires an Internet connection 

through the Envoy. Failure to maintain an Internet connection may 

have an impact on the warranty. See 

enphase.com/warranty

 for full 

terms.

• 

Wireless communications kit (COMMS-KIT-EU-01) to be installed at 

the Envoy for communications with Encharge. Includes USB cable for 

connection to  Envoy along with communication extender and allows 

wireless communication with Encharge

D )  Make sure you also have the following 

required items

:

• 

Mounting location that is structurally suited to bear the weight of the 

Encharge Battery(ies). Total weight for the Encharge 3T, including the 

Encharge base unit, cover and wall mount bracket, is 48.8 kgs. Total 

weight for the Encharge 10T, including the three Encharge base units, 

cover, and wall mount bracket, is 143.6 kgs.The wall must contain 

blocked studs that can bear the battery weight or can be of masonry 

or other suitable structure.

• 

Tools: conduit (with fittings and fitting tools), drill, 4 mm pilot bit, 

screwdriver, socket wrench, torque wrench, level, wire stripper, and 

stud finder if installing on studs.

• 

Fasteners for wall mount bracket. Slots are 9.2 mm. Check with a 

structural engineer and local standards for requirements:

  Single-width bracket for Encharge 3T: A minimum of three #8 mm lag 

bolts or screws, 7.6 cm long (depending on attachment wall). 

  Triple-width bracket for Encharge 10T: A minimum of nine #8 mm  lag 

bolts or screws, 7.6 cm long (depending on attachment wall). 

• 

Washers for use between fastener heads and wall-mount bracket.

• 

Copper conductors: 2.5 - 10 mm

2

 (11mm strip length) copper 

conductors (rated at 75° C or 90° C) for terminals.

• 

Conduit fittings: 12 mm or 20 mm (left side) terminators are required 

for all installations, and IP54 conduit fittings are needed when 

installing outdoors.

• 

Over current protection: The overcurrent protection in Encharge is not branch 

circuit overcurrent protection and cannot be relied upon for that purpose. The 

branch circuit overcurrent protection SHALL be located separately.

• 

Personal protective equipment (PPE) for handling lithium batteries as 

required by local safety standards. 

• 

Protective gloves for protection against sharp edges.

E )  Verify that main service is 230 V L-N. Encharge batteries cannot be installed 

between L1 and L2. 

F )  Note that the rated energy capacity of the battery is 3.5 kWh.
G )  Install the PV system as directed by the Enphase installation manuals. 

Power Line Communication

Содержание ENCHARGE-3T-1P-INT

Страница 1: ... care when lifting The Encharge Battery unit is heavy 40 5 kg and requires two persons to lift C Ensure you have the following required Enphase items The Enphase Encharge system requires an Internet connection through the Envoy Failure to maintain an Internet connection may have an impact on the warranty See enphase com warranty for full terms Wireless communications kit COMMS KIT EU 01 to be inst...

Страница 2: ...according to local codes standards and other applicable requirements The subpanel could be a small two circuit box with circuit breakers The circuit breakers in the box would have to be suitable for back feeding per local grid connection regulations Select the right size subpanel and breakers based on the number of Encharge units being installed To do this you must purchase an off the shelf subpan...

Страница 3: ...ds WARNING Risk of injury and equipment damage Use the unit mounting holes only to mount the base unit of Encharge to the wall mount Do not use the unit mounting holes to secure the bracket to the wall B Use a level to keep the bottom of the wall mount bracket level C Use 20 8 mm screws or masonry attachments for masonry to attach the bracket using one screw and washer for each slot 9 2mm Use a mi...

Страница 4: ...w hole DC Switch d c a b Prepare for field wiring DANGER Risk of electric shock The DC switch must be in the Locked position before performing this step A Drill the left wall of field wiring compartment to accommodate the conduit B Connect field wiring to the top three terminal blocks C Size the conductors Line Neutral and Ground to account for voltage rise and to conform to the tables below Desig...

Страница 5: ...for assemby and disassembly of Encharge 3T cover simillar instructions are applicable for Encharge 10T cover A Check that the field wiring compartment cover s for all Encharge Batteries in the system are closed and secured DANGER Risk of electric shock Before continuing check that Encharge units are properly wired and ground connection does not have a L or N connection as this introduces a safety ...

Страница 6: ...rpose the Enchage 10T Cover image is shown above for locking 8 Before pushing into place Locked into place F After assembling the Encharge cover remove the break out tab from the conduit cover and assemble with the ribs snapping in as shown G Break the conduit cover tab along the yellow line as indicated before assembling to the main unit 9 Disassembly of the Encharge Cover A Remove the conduit co...

Страница 7: ...he Enphase Installer Toolkit to commission the Encharge Battery ies Once connected to the Envoy refer to the Installer Toolkit help topics for more information B After the Envoy has detected the Encharge Battery ies the Encharge LEDs operate as described in the following section CONFIGURE and ACTIVATE OPERATION a LED overview After being commissioned the LED flashes yellow while each Encharge Batt...

Страница 8: ...charge Battery ies to liquids or flooding WARNING When placing the Encharge Battery ies in storage ensure that AC power is not present and that the DC switch is in the Locked position While in storage damage to the battery can occur from over discharge If the battery state of charge falls to 0 the Encharge Battery ies can be damaged or destroyed Because of this the Encharge Battery ies must only b...