Replacing the E3 PCBA from the IQ System

 

To replace IQ System Controller, read and follow all warnings and instructions in this guide. Safety warnings are listed on the back of this guide. These instruc-

tions are not meant to be a complete explanation of how to design and install an energy storage system. 

All installations must comply with national and local electrical codes and standards. Only qualified electricians shall install, troubleshoot, or replace the IQ Sys

-

tem Controller. 

All service or maintenance operations on the IQ System Controller unit should be performed only by trained and qualified personnel who understands and fol

-

lows the required safety codes and use adequate Personal Protective Equipment (PPE). 

WARNING! 

The following procedure is to be performed only when the grid is functional and the Enphase system has not formed a microgrid. 

WARNING! 

Failure to follow this warning could cause personal injury or death. Before performing service or maintenance operations on unit, always turn off 

main power switch  to unit and install lockout tag. Unit may have more than one power switch. 

© 2021 Enphase Energy. All rights reserved. Enphase, the Enphase logo, IQ System Controller, IQ Battery, IQ Gateway, IQ combiner, IQ microinverter, Enphase App 

and other trademarks or service names are the trademarks of Enphase Energy, Inc. Data subject to change. Rev01-10-23-2021

Tools and parts to be used:

        Open the IQ System Controller and remove the Dead-

front

A )  Open the three latches that lock the enclosure door. To release the 

latch, pull the latch handle forward and then to the right. With all the 

latches opened, swing open the enclosure door.

B )  Use a Phillips Size #2 screw driver to loosen the six screws along the 

periphery of the deadfront. Support the deadfront to keep it from falling 

while performing the next step. 

C )  While supporting the deadfront, use a blade screwdriver to disconnect 

the deadfront ground wire from the grounding bar before removing the 

deadfront.

D )  Use the two tabs on the front to assist handling the deadfront during 

dismantling.

E )  Remove deadfront from the IQ System Controller unit and place it aside 

safely.

2

       Open the Controller PCBA Cover

A )  Locate the Zigbee antenna cable zip tied to right side of the E3 cover 

(metal cover) as shown in 

Figure 1

. Using the small wire cutter cut the 

zip-tie tied between E3 Cover and Zigbee antenna cable.

                

NOTE:

1.  Mark the zip tie location on antenna cable using a sharpie for easy 

locating while reinstalling zip-tie.

2.  Pay attention to only cut zip tie, do not cut or damage the antenna 

cable or the EMI sheet wrapped around the cable.

3

B )  Unscrew the 4 screws on top of E3 cover. Do not remove the ground 

(green) cable (indicated in 

Figure 2a

)  connected on the left side of E3 

cover. Remove and secure the E3 cover on left side empty space as 

shown in 

Figure 2b

.

NOTE:

 Do not disconnect ground wire connection to E3 cover. 

S.No

Component

Qty

Source of part

1

E3 replacement PCB

1

Provided in kit

2

Zip tie

2

Provided in kit

3

Serial number label- for E3

1

Provided in kit

4

Serial number label- for IQ System 
Controller

1

Provided in kit

5

Spare Zigbee antenna assembly

1

Provided in kit

6

Philips Screwdriver (Size #2)

1

Arranged by installer

7

Flat head Screwdriver (any size)

1

Arranged by installer

8

Multimeter

1

Arranged by installer

9

Sharpie

1

Arranged by installer

10

Wire cutter

2

Arranged by installer

11

Step Ladder

1

Arranged by installer

12

ESD Protective hand gloves

1 pair

Arranged by installer

PROCEDURE

Figure 2a: E3 cover with ground 

wire indicated             

Figure 2b: E3 cover after being 

removed 

Figure 1: 

Zigbee Antenna tied to the side of the E3 cover

        De-energizing the IQ System Controller 

A )  Turn DC switches in IQ Batteries to OFF. ( For instruction on opening IQ 

Battery cover please refer to the following document  

https://enphase.

com/sites/default/files/2021-04/IQ Battery3-10-QIG-EN-US.pdf

).

B )  Open IQ Battery breaker in IQ System Controller. 
C )  Open PV breaker in IQ System Controller.
D )  Open the mains breaker.
E )  Disconnect the grid source power supply (breaker in main panel).
F )  Open generator breaker.
G )  Use multi meter to measure AC voltage on all the following terminals – 

PV, IQ Battery, Grid , Load and Generator. It is safe to work on IQ System 

Controller only when no voltage is detected on any of these terminals 

and you have ensured that all IQ Battery units have DC powered off.

1

Содержание E3 PCBA

Страница 1: ... E Remove deadfront from the IQ System Controller unit and place it aside safely 2 Open the Controller PCBA Cover A Locate the Zigbee antenna cable zip tied to right side of the E3 cover metal cover as shown in Figure 1 Using the small wire cutter cut the zip tie tied between E3 Cover and Zigbee antenna cable NOTE 1 Mark the zip tie location on antenna cable using a sharpie for easy locating while...

Страница 2: ...age the board The approximate Torque needed is 0 7 N m 6 2 lb in J Insert another cable tie through the hole on the right side of the E3 cover K Secure the Zigbee antenna cable to the E3 cover as shown in Figure 4 5 Figure 4 Zip tie pulled through E3 Cover Figure 5 Antenna cable position in IQ System Controller Remove the E3 PCBA and Insulator A Make sure to wear ESD protection gloves before handl...

Страница 3: ...turn the breaker feeding the IQ System Controller to ON position H Close and secure the door of the IQ System Controller I The E3 PCBA replacement kit comes with stickers which will have new serial numbers for the IQ System Controller Please remove the older serial numbers and paste the new ones in its place A Reconnect the deadfront ground cable to the grounding bar torque as shown in Table 1 B R...

Страница 4: ...ion NOTE To ensure optimal reliability and to meet warranty requirements the IQ System Controller must be installed and or stored according to the instructions in this guide NOTE The IQ System Controller is compatible only with the IQ Gateway or Envoy S metered communications gateway properly fitted with USB hub USB radios and production and Consumption PCS CTs The Envoy is required for operation ...