background image

  I N S T A L L A T I O N   I N S T R U C T I O N 

Installing 

Enphase 400A Production CTs

Use this instruction with the 

Enphase IQ Gateway Commercial 2 Quick Install Guide

 to install Enphase production monitoring Current 

Transformers (CTs). The Enphase IQ Gateway Commercial 2 uses a set of three 400A solid core CTs for monitoring solar production current. 

This CT performs metering with accuracy class of 0.2%. Rated at Pollution Degree 3, you can use the CT inside electrical equipment in residential 

or in harsh, industrial conditions. Read and follow all warnings and instructions in this instruction and in the Quick Install Guide included with your 

Gateway and available at: 

https://enphase.com/installers/resources/documentation

INSTALLATION

For more information, refer to the 

IQ Gateway 

Commercial 2 Quick Install Guide

 available at: 

https://enphase.com/installers/resources/

documentation.

Preparation

A )  If not already done, turn off  

power to the PV system.

Remove any pre-installed production CTs

A )  Remove the line 1, line 2 and line 3 conductors of the solar produc-

tion circuits on which the CTs are connected.

B )  Remove the existing CTs.

Install the production CTs

A )  Before running the CT wires through the conduit, use colored tape to 

mark one of the CTs and the free end of its wires. 

B )  For each CT, locate the arrow on the CT label. 
C )  Refer to the diagram on the reverse of this document for wiring.
D )  Install the production CTs on active phases as required:

• 

Locate the arrow on the CT label.

• 

To monitor production on Line 1

Connect the white wire to the white “P1” terminal and the blue 

wire to the blue “P1” terminal.

Pass Line 1 of the solar production circuit through the CT with 

the arrow pointing toward the load (away from the solar array).

• 

To monitor production on Line 2

:

Connect the white wire to the white “P2” terminal and the blue 

wire to the blue “P2” terminal. 

Pass Line 2 of the solar production circuit through the CT with 

the arrow pointing toward the load (away from the solar array).

• 

To monitor production on Line 3

:

Connect the white wire to the white “P3” terminal and the blue 

wire to the blue “P3” terminal.

Pass Line 3 of the solar production circuit through the CT with the 

arrow pointing toward the load (away from the solar array). 

 

Tighten all connections to 5 in-lbs (0.6 N m).

E )  Close and secure the terminal block door of the Gateway.
F )  Turn on the PV system.

SAFETY

SAFETY AND ADVISORY SYMBOLS

+

DANGER

: This indicates a hazardous situation, which if not avoid-

ed, will result in death or serious injury.

NOTE

: This indicates information particularly important for opti-

mal system operation. Follow instructions carefully.

SAFETY INSTRUCTIONS

+

DANGER

: To reduce the risk of electric shock, always open or 

disconnect circuit from power-distribution system (or service) of 

building before installing or servicing current transformers.

+

DANGER

: Risk of electrocution! Do not install CTs when current 

flowing in the sensed circuit. Always install CT wires in the termi

-

nal blocks before energizing the sensed circuit.

+

DANGER

: If equipment is used in a manner not specified by 

Enphase Energy, the protection provided by the equipment may 

be impaired.

+

DANGER

: Risk of electric shock.  Be aware that installation of 

this equipment includes risk of electric shock. If you wire the IQ 

Gateway at the subpanel, always de-energize the subpanel before 

beginning.

+

DANGER

: Risk of electric shock. Risk of fire. Only qualified per

-

sonnel should troubleshoot, install, or replace the CTs.

NOTE: 

Because of variance in switchboard design and main power 

feed, there may not always be enough space to install CTs.

NOTE

: Do not install the CTs in a switchboard where they exceed 

75% of the wiring space of any cross-sectional area within the 

equipment.

NOTE

: Perform all electrical installations in accordance with all 

national and local electrical codes.

NOTE: 

Restrict installation of current transformers in an area 

where they would block ventilation openings, or in area of breaker 

arc venting.

NOTE:

 Not suitable for Class 2 wiring methods and not intended 

for connection to Class 2 equipment.

NOTE: 

Secure current transformer and route conductors so that 

they do not directly contact live terminals or bus.

NOTE: 

When wiring the IQ Gateway Commercial 2 for production 

and consumption metering, be sure to install the current trans-

formers (CTs) exactly as described for your application.

NOTE: 

When installing CTs, it is important to match CT and sense 

voltage phases. Be sure to consistently identify the three AC lines 

at three points: the main load center feed, the Gateway, and the 

solar production circuit breaker. Wire colors (typically black, red 

and blue) may not always consistently identify L1, L2 and L3. If in 

doubt, use a multimeter to check.

NOTE: 

Only run active conductors through the CT. The CT can 

monitor multiple active conductors. You may run more than one 

wire through the CT if all wires are on the same phase and they fit 

the opening in the CT.

NOTE: 

For indoor use only.

SPECIFICATIONS

SPECIFICATION

CT-400-SOLID

CT type

Solid core

CT accuracy (error rate) 

<0.5%

Max primary supported current

400A

Turns ratio

2000

Pollution degree

3

Dimensions

2.99inch diameter * 0.712inch thickness

Aperture

1.69inch diameter

Supported Cable Size

Up to a maximum size of 1000KCMIL 

conductors.

Primary voltage (range)

250VAC max

Frequency

50-60Hz

Operating temperature

-40 to 85 degree C

Humidity

95%

Pollution degree

3

Compliance

ROHS(latest version) 

Отзывы: