2. After installing support bars on each of the 4 modules, number each module #1 to #4.
Module #1 will be the bottom module in the stack.
3. Install 3 mounting beams on module #1 (the bottom module) using M12 bolts and M3
screws—note that beams fasten onto the same side of the module frame as the gapped
support bars installed previously, which is also the side closest to the negative terminals.
On module 1 only, install the baffle board in the gap between the support bars. M12
bolts should be torqued to 42 Nm (428 kgf
ꞏ
cm) while M3 screws should be torqued to
0.63 Nm (6.42 kgf
ꞏ
cm).
Figure 7
Install Mounting Beams and Baffle on Module #1
Beams
Baffle
Содержание Outback Power EnergyCell 1000XLC
Страница 1: ...EnergyCell 1000XLC Owner s Manual...
Страница 10: ...Introduction 10 900 0258 01 00 Rev A This page intentionally left blank...
Страница 28: ...Operation 28 900 0258 01 00 Rev A NOTES...
Страница 32: ...Troubleshooting and Maintenance 32 900 0258 01 00 Rev A NOTES...
Страница 35: ...EnergyCell Batteries 900 0258 01 00 Rev A 35 This page intentionally left blank...
Страница 36: ...Masters of the Off Grid First Choice for the New Grid 17825 59th Avenue N E Suite B Arlington WA 98223 USA...