Stamolys CA71CODcr
Commissioning
Hauser
31
6
Commissioning
6.1
Function check
CAUTION
!
Avoid damage due to incorrect power supply and inaccurate or insecure hose
connections
►
Check that all connections are secure. In particular, ensure that all hose connections are secure,
so that no leaks occur.
►
Ensure that the power supply voltage corresponds to the voltage specified on the nameplate.
6.2
Switch-on
CAUTION
!
Inappropriate handling of the waste containers can cause chemicals to leak and pose a
threat to humans and the environment
►
The waste containers must be secured in place under the analyzer to ensure correct operation.
►
Prior to commissioning, you must fill the container for the chromate waste with the detoxicant
(reagent 3, CAY440 or CAY441).
When the analyzer has been configured and calibrated, the measuring cycle starts automatically.
Entering parameters is no longer necessary.
To perform initial startup or to readjust the device parameters, proceed as follows:
1.
Plug-in the plug into a socket.
2.
Press the
H
key until AUTO MEASURING is displayed.
• Preheat the analyzer in the AUTO MEASURING mode.
• At the start of measurement with a cold analyzer, new hoses, longer interruption of the
measurement or variable measurement cycles, the first measuring results will be errored. The
reaction is temperature-dependent and if the temperature is too low the predefined reaction time
is insufficient for a complete reaction. For this reason, never carry out calibration with a cold
analyzer. Wait for two or three measurements to be taken before carrying out calibration.
• The accuracy mode and increased rinse cycles improve the repeatability and accuracy of the
measurement.
3.
Select the CONFIGURATION menu and configure all the parameters up to and including
"Tank capacity".
With
H
you can return to the main menu.
4.
Now work through the PARAMETER ENTRY menu.
5.
Go to the SERVICE menu.
NOTICE
Incorrectly combined function controls can damage the analyzer.
►
When using the manual operation via the Service menu, make sure that chloride-containing
sample never gets in contact with reagent R2 in the reactor. Otherwise precipitating silver
chloride can cause film or coating on the optical windows, which would result in measuring
errors.
►
Make sure you have detailed knowledge of how the analyzer works and operates before you
make any settings in the Service menu.
►
Exit the Service menu with the "M" key. All functions will be reset to the delivery state then.