Oxymax H COS21
Commissioning
Hauser
7
3.2
Post-connection check
4
Commissioning
4.1
Function check
Before first commissioning, check if:
• the sensor is correctly installed
• the electrical connection is correct.
If using an assembly with automatic cleaning, check the correct water connection at the
assembly rinse connection.
#
Warning!
Danger of medium leaking off
Before applying compressed air to an assembly with cleaning facility, make sure the connections
are correctly fitted. Otherwise, the assembly may not be insert into the process.
4.2
Polarization
The sensor was tested in the factory for perfect functionality and is supplied ready for operation.
To prepare for calibration, proceed as follows:
1.
Remove the sensor protective cap.
2.
Place the externally dry sensor in atmospheric air. The air should be saturated with water
vapour. Therefore, install the sensor as close to the water surface as possible. When
calibrating the sensor membrane, make sure the membrane remains dry. Therefore, avoid
any direct contact with the water surface.
3.
Connect the sensor to the transmitter and switch on the transmitter.
Instrument status and specifications
Remarks
Are the sensor, assembly, junction box or cable damaged?
Visual inspection
Electrical connection
Remarks
Are the installed cables strain-relieved and not twisted ?
Is the cable type route completely isolated ?
Power cable/weak current cable
Are the power supply and signal cable correctly connected to the
transmitter ?
Use the connection diagram of the transmitter.
Are all the screws terminals properly tightened ?
Tighten
Are all the cable entries installed, tightened and sealed ?
For cable entries lateral: cable loops downwards
for water to be able to drip off.
Are all the cable entries installed downwards or lateral ?