Installation
LT5
64
Hauser
5.13 Liquid sealant for seal pot
5.13.1 Filling seal pot with liquid sealant when installing a new
gauge
Liquid sealant filling procedure
1. Install the entire LT system, including the seal pot and float.
Parts of the diagram below may vary, depending on the order code that was
selected.
2. Hoist the float up and down manually to confirm that the dial (or counter) display
changes accordingly.
230
(9.06)
950 (37.4)
440
(17.32)
220
(8.66)
220
(8.66)
250 (9.84)
2000 - 3000
(78.74 - 118.11)
300
(11.81)
109 (4.29)
Ø400
(15.74)
1200 (47.24)
1200 (472.4)
1
2
3
4
11
12
13
14
A
5
6
7
8
9
10
A0041198
51
LT with seal pot. Unit of measurement mm (in)
A
Anchor hook
1
Top anchor
2
Measuring tape
3
Float
4
Guide wires
5
Nut
6
Welded part (welded to the tank)
7
Anchor hook
8
Guide wires
9
Bolt
10 Washer
11 Seal pot
12 90 ° sheave elbow
12 Gauge supporter
13 Gauge head