Installation preparation
Be sure to perform the following operations prior to installing LT.
• The gauge head should be installed in a place where the meter can be read easily.
• The float must be installed so that it is positioned near the tank's side wall.
• In a spherical tank, the float must be installed so that it is positioned near the center of
the tank.
• If the roof of a dome-roof tank has a steep incline, the float must be installed so that it is
positioned near the center of the tank.
• Use an appropriate gasket on the flange connection to maintain airtightness.
L
CAUTION
Risk of tape severing
‣
The float should be positioned as far from the tank inlet or stirrer as possible so that
the waves do not directly impact the float. If there is no choice but to position the float
near the inlet or stirrer, install a wave guard to protect the float. Rapid injection of
liquid near the float may cause the tape to sever.
1
2
3
4
2
4
4
4
A0039946
11
Installation conditions
1
Center of the float
2
Wave guard installation
3
Tank
4
Liquid inlet