Figure 3-8 Lift the cabinet off the pallet
Step 4
: Remove the cabinet from the pallet and place it in the specified position.
3.3.
Installation
In this section, the installation and commissioning will be explained in detail. Ensure
that all the installation tools and fittings are available prior to installation.
Attention
Following are some safety measures that must be observed prior to installation of the
Edge Rack 3P system:
●
Before installation, ensure that the installation site is clear. The site gradient level
has to be confirmed and should meet the requirements.
●
Switch off the power during installation. Operation on any electrified equipment is
forbidden. The connecting cable must comply with related requirements.
3.3.1.
Installing the cabinet
Following are the steps that need to be observed while installing the cabinet:
Step 1
Measure the height from the ground to the top of the cabinet channel with
a tape measure. By adjusting the leveling feet, make sure the height of the cabinet
is from 2030 mm to 2033 mm.
Step 2
Raise the leveling feet so that the casters touch the ground, Slide the
cabinet into the installation position.
21