9.8
Planned maintenance tasks
Planned maintenance tasks
Table 9-2:
Task
Recommended action
Inspect
Implement a periodic inspection program to ensure all parts
are free from damage due to process, ambient or other ab-
normal conditions.
•
Internal components: rotor, upstream to downstream
cone, etc.
•
Meter body housing, external flanges, flamepath.
•
Bolting
•
Electrical connections.
Clean
Use a non-toxic metal cleaning solvent.
Do not use common petrochemical solvents like Benzene,
Toluene or Xylene as they can pose potential health hazards.
Monitor corrosion / erosion / wear
A careful review of turbine meter proving history, such as
turbine meter factor control charts, can reveal potential
problems with turbine meter measurements. Examples in-
clude bearing drag due to wear or an increased internal
cross-sectional area due to erosion.
Planned maintenance
84
Daniel Series 1500 Liquid Turbine Meter, NPS 3-24
Содержание daniel 1500 series
Страница 1: ...User manual P N 3 9008 515 Rev D July 2016 Daniel Series 1500 Liquid Turbine Meter NPS 3 through 24 ...
Страница 8: ......
Страница 12: ...Plan 2 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 64: ...Prepare the turbine meter for use 54 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 66: ...Install 56 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 72: ...Installation procedure 62 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 74: ...Testing 64 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 75: ...Part III Operate Operate User manual 65 ...
Страница 76: ...Operate 66 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 80: ...Maintain 70 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 101: ...Decommission the turbine meter User manual 91 ...
Страница 102: ...Decommission the turbine meter 92 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 103: ...Decommission the turbine meter User manual 93 ...