7
Testing
7.1
Test the turbine meter
7.1.1
Commission the turbine meter
After installation, commission the turbine meter to ensure that the equipment is working
properly.
1.
Inspect all electrical connections to ensure compliance with electrical codes and
safety regulations.
2.
Inspect all flange bolts used to secure the turbine meter in-line to ensure that
correct mounting procedures are followed and that flange connections are leak-
free.
3.
Evaluate the system setup to ensure that all components are in the correct sequence
for accurate product measurement: isolation valve, strainer, flow straightener,
turbine meter, downstream section, control valve, etc.
4.
Ensure that the supply voltage to the preamplifier is within the 10-30 VDC range.
Testing
User manual
63
Содержание daniel 1500 series
Страница 1: ...User manual P N 3 9008 515 Rev D July 2016 Daniel Series 1500 Liquid Turbine Meter NPS 3 through 24 ...
Страница 8: ......
Страница 12: ...Plan 2 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 64: ...Prepare the turbine meter for use 54 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 66: ...Install 56 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 72: ...Installation procedure 62 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 74: ...Testing 64 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 75: ...Part III Operate Operate User manual 65 ...
Страница 76: ...Operate 66 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 80: ...Maintain 70 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 101: ...Decommission the turbine meter User manual 91 ...
Страница 102: ...Decommission the turbine meter 92 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Страница 103: ...Decommission the turbine meter User manual 93 ...