BOILER CONTROL: INTERNAL WIRING & OPERATION
8. BOILER CONTROL: INTERNAL
WIRING & OPERATION
A. CONTROL OVERVIEW
The Peak boiler control is one of the primary safety devices for
the boiler. It controls:
• Ignition sequence
• Temperature Limits
• Circulators
• Gas Flow
• Setpoints
• Domestic Hot Water Valve
• Fan Speed
• LWCO (When optional LWCO probe is used)
B. AVAILABLE CENTRAL HEAT MODES
Table 8.1: Peak Central Heat Modes
Central
Heating
Mode
Mode Description
Mode Operation
Restrictions
0
Fixed Setpoint
– Demand initiated by T/TT closure
– User chosen fixed setpoint
– Boiler targets CH setpoint and operates of Supply
temperature hysteresis when demand is present
Not for space heating
1
Outdoor reset with Thermostat
– Demand initiated by T/TT closure
– Setpoint is calculated based off of Outdoor temperature
and CH demand period to improve fuel usage and boiler
efficiency.
– Setpoint Boost function for long CH demand periods.
– Boiler targets calculated CH setpoint and operates off of
Supply temperature hysteresis when demand is present
– When the Boost Function was active and CH demand
is not present, the CH setpoint decreases back to the
calculated setpoint.
No restrictions
2
Outdoor reset with Permanent
Demand
– Demand initiated by control logic. Always present.
– Setpoint is calculated based off of Outdoor temperature to
improve fuel usage and boiler efficiency.
– Boiler targets calculated CH setpoint and operates off of
Supply temperature hysteresis.
– When CH demand is not present, calculated setpoint
decreases gradually.
No restrictions
3
Fixed Setpoint with Permanent
Demand
– Demand initiated by control logic. Always present.
– User chosen fixed setpoint
– Boiler maintains CH setpoint and operates of Supply
temperature hysteresis.
Not for space heating
*While accessible via the Installer menu, CH Modes 4 and 5 are not functional with the Peak boiler.
Содержание Peak-40
Страница 22: ...22 WATER PIPING AND CONTROLS Figure 4 6 Recommended Central Heat Piping ...
Страница 23: ...23 WATER PIPING AND CONTROLS Figure 4 7 Recommended Central Heat Piping with Hydronic Separator ...
Страница 24: ...24 WATER PIPING AND CONTROLS Figure 4 8 Recommended Domestic Hot Water Piping ...
Страница 33: ...33 ELECTRICAL CONNECTIONS Figure 7 4 Wiring Schematic and Connection ...
Страница 47: ...47 START UP PROCEDURE E LIGHTING OPERATING PROCEDURES ...
Страница 59: ...59 THIS PAGE INTENTIONALLY LEFT BLANK ...
Страница 62: ...62 REPAIR PARTS Figure 13 2 Peak 40 LP Combustion Components ...
Страница 64: ...64 REPAIR PARTS Figure 13 3 Peak 40 NG Combustion Components ...
Страница 66: ...66 REPAIR PARTS Figure 13 4 CHB Parts Detail ...
Страница 68: ...315 Oser Avenue Hauppauge NY 11788 Tel 631 694 1800 Fax 631 694 1832 www embassyind com ...