Gold Solo Double Twitter Installation Guide
MAN-G-SOLTWIB_160 (Ver. 1.005)
|
Main, Control, and Motor Power|
www.elmomc.com
26
Table of Contents
Chapter 8:
Connections
8.1.
Main, Control, and Motor Power
This section describes the Main and Control supplies, and Motor Power connections. The Motor and
Main Power interface uses lugs and cables defined in section 7.2.1 Recommended Cable Lugs and
Cabling.
8.1.1.
Connecting the DC Power and the Motor Power Wires
This section describes the installation of the wire terminal lugs for both the Main Power wires to
VP+, PR, and PE terminals on the Gold Solo Double Twitter, and the Motor Power wires to the M1,
M2, M3, and PE terminals on the Gold Solo Double Twitter.
Note:
When connecting several identical motors, all the motor phases must be connected in an
identical sequence in order to save repetition of the tuning process.
Step 1: PE Earth Connection
Tighten the screw to the relevant torque force applicable to an M3 stainless steel A2 screw.