Mounting of shaft mounted drives
CAUTION!
Observe the following safety instructions.
Failure to observe them can lead to bodily injuries!
Risk of injury due to electrocution.
• The connections to the 230 V/400 V mains
must
be made by an electrician.
Check the rated voltage before making the electrical connection (3~400 V; 3~230 V or 1~230 V).
• Only use unmodified original
elero
®
plug-in connecting cables.
• Before accessing the connection terminals all mains circuits must be switched off.
Check that there is no power.
• During installation, operation and when working on the equipment, it must be possible to isolate all poles of the power
supply (all-pole switch with at least 3 mm contact gap or all-pole main switch).
• The regulations of the local energy supply company as well as the regulations for wet and damp rooms according to
VDE 0100 must be followed when making the connections.
• In order to ensure the given strain relief and degree of protection always carefully tighten the cable glands and the
screws of the limit switch cover.
• The pluggable parts have to be completely inserted.
• The control of the sense of rotation and the limit switch settings should only be undertaken in “Control without
maintained mode“ (dead-man‘s safety system).
• Ensure that the door is not moved beyond the operating limit switches.
3.15 Electrical connection
3.14 Mounting of shaft mounted drives
Shaft mounted drives
Install rolling door guide rails and wall brackets or plate
bearing surfaces.
1.
Install the brackets on the opposite side. The bracket
must
be installed higher by a dimension “X” (see figure).
2.
Align and weld the welding shaft with the blanks and the
adjustable counterpart support to the winding tube.
The material of the winding tube must be welding
material meeting the standard DIN 17100.
X = Height difference
Drive bracket - counterpart bracket
3.
Install the drive and the pedestal bearing.
To connect drive and bracket use hexagonal bolts
M 12 x 30 DIN 933 8.8, nuts M 12 DIN 934, spring
washers A 12 DIN 127, washers A 13 DIN 9021.
Insert the winding tube with the welding shaft and the key
into the hollow shaft. Do not wedge up using force!
Insert the adjustable counterpart support into the bearing
and lock permanently in both axial directions to prevent
displacement. The drive bracket is carried in pendulum
bearing and compensates for the out-of-round running of
the winding shaft.
4. Fix the rolling door curtain to the winding shaft.
5.
Install control casing in accordance with the manufacturer’s
guidelines.
6.
Insert the limit switch cable in the limit switch housing of
the drive! Do not engage the cover yet.
7.
Unscrew the terminal box cover on the motor and connect
the motor cable. Replace the cover and fasten the screws.
8. Switch on the mains.
9.
Check the sense of rotation.
Press the UP button briefly. The door
must run in upward
direction. If this is not the case, disconnect the mains
supply to the control unit and swap phases L1 and L2.
After that switch on the mains again.
– omitted for WF .., single-phase motors
The welding shaft with blanks must be welded centrally in the winding shaft.
Mount the drive properly on a bracket or a torque absorber of sufficient strength, compatible to the permissible stop torque of
the drive, using two screws M 12 x…/ strength class 8.
Grease the hollow shaft before installation and plug in the winding shaft using the plug-in shaft and key.
Do not wedge up using force!
Before mounting the rolling door, the winding shaft must be secured permanently against axial displacement at the
counterpart support at both ends!
Do not secure the winding shaft axially on the shaft mounted drive!
NOTE!
Pedestal bearing
e.g. column