Vehicle Cable Management
For the connector whips between the tracks and between the front track and camera, it is recommended
that the connector cable be looped and strapped to the push interconnects using standard cable ties as
shown below:
Optional Traction Arm Springs
The spring loaded VT50
™ traction arms have been optimized for a 2in [50mm] pipe size. If additional
traction is required in the larger pipe sizes, stiffer springs (P/N 3050836) may be installed as follows:
1. Remove all four spring hangers and standard springs
2. Fasten one end of each spring to the forward spring hanger (on the traction arm) and screw down
flange
3. Using a thin screw driver or pick, stretch the other end of the spring onto the rear spring hanger
and screw down flange
4. Use Loctite 243 (blue) with all the screws.