EcoSource Low Voltage Installation
Figure 20: EcoSource Backplate with UL-Rated Insulating Tape
JBOX Using Horizontal Mud Ring
Instructions
Requires:
•
Speed nut that accommodates a #6-32 1” screw.
•
two #6-32 1-inch screws
•
1 hole to be drilled into backplate (drilling performed onsite or by Telkonet Production prior to
shipping if requested in advance.)
Step 30
Ensure the JBOX has been installed with a horizontal mud ring.
Step 31
Unless this was done prior to shipping, drill a hole in backplate as shown in Figure 21. The
horizontal distance between the hole and the inner right side of the plate should be 1.0”. The
vertical distance between the hole and the inner right side of the plate should be 1 ¾”. The
hole should accommodate a #6-32 1” screw.
(Preferred method for low voltage new construction)
EcoWave Featur ing EcoTouch IO&M Guide
Telkonet, Inc.
For Use w ith Fir mw ar e Ver sion 2.x
20800 Sw enson Dr ive, Suite 175
EcoSour ce
Waukesha, WI 53186
Revision 2
(800) 380-9640
Page 20
w w w .telkonet.com