Another possible setting is
complete system HPLC (box, pump, column oven, detector)
.
Each unit from the HPLC system has among its accessories all necessary parts for interconnection
of entire waste system. On picture below is shown complete waste system and detailed picture of
the pump.
All parts of waste system are parallel with unit
lateral sides, neatly connected without twisting, so that
the waste liquid may fluently run down to waste
reservoir. In the tubing junctions with connectors may
accumulate liquid, that after a while flows through
connector openings.
Interconnetion of waste system between box and
pump is similar as described above. Difference is in
using shorter tubing of part 2, placed behind injection
valve holder, and the longer tubing remains in front of
the holder. Connector Y of part 2 should be connected
with a part of column oven accessories (connector Y
connected with connector L and tubing). Press
connector L into waste channel of the pump. Connect
tubing with a part of detector accessories (two
connectors Y joint with connector L, tubing and
connector I). Connector L connected with connector Y
should be pushed into waste channel of column oven.
Connector Y with a tubing carries out the mobile phase
from detector and connector I joint with tubing carrying
liquid into waste reservoir (see above). Its part is a
tubing joining connector L, pushed into waste channel of
detector.
Note:
New setting is leaking at the beginning. It stops after some time.