background image

E93.9950EN CB Cascade manual 

9

 

Figure 4.2 Dimensions: side views 

After you have determined which cascade configuration will be applied and therefore how many boilers must be 
combined in the cascade configuration, the next step is to determine the total dimensions of the cascade 
configuration and the space required for the cascade configuration. 

Figure  4.1  and  Figure  4.2  show a schematic representation of a cascade configuration. The dimensional 
references in this figure (L1-L3, H1-H3, D1-D3, A, B) correspond with the dimensional references in the tables 
below.  

E

XAMPLES

 

In case a cascade configuration  for 275 kW is required,  which will exist of 2 boilers, refer to Table  4.1  for the 
dimensions of the cascade configuration. The table shows that frame length for this configuration  is 1030 mm 
and the total length including the low loss header is 1428 mm. 

In case a cascade configuration  for 440 kW is required,  which will exist of 4 boilers, refer to Table  4.2  for the 
dimensions of the cascade configuration. The table shows that frame length for this configuration  is 2010 mm 
and the total length including the low loss header is 2408 mm.  

All these dimensions have to be taken into account when determining the space required for placing the 
cascade configuration. 

EHS.T0200.5050

 

Bolts can be adjusted max. 50 mm 

EHS.T0200.5050

 

Содержание CB 85 CH

Страница 1: ...Installation manual CASCADE SETUP Wall hung high efficiency central heating boilers CB 85 CH CB 105 CH CB 125 CH CB 155 CH INITIAL VERSION E93 9950EN S67 500 004 003 03...

Страница 2: ......

Страница 3: ...UNTING THE FRAME 15 8 1 Frame elements 15 8 2 Procedure for mounting the frame 16 9 MOUNTING THE GAS HEADER 17 10 MOUNTING THE BOILERS ON THE FRAME 18 11 MOUNTING THE HYDRAULIC GROUP AND THE CONNECTIN...

Страница 4: ...ne boiler go into error the cascade configuration will continue to operate ECO Heating Systems can supply standard cascade systems with mounting frame piping and low loss headers for up to six boilers...

Страница 5: ...d in detail in chapter 8 4 Mount the gas header This is described in detail in chapter 9 5 Mount the boilers on the frame This is described in detail in chapter 10 6 Mount the hydraulic group and the...

Страница 6: ...9 2 2 CCB 249 2 0020 253 1 1 2 CCB 253 2 0101 255 3 3 CCB 255 3 3000 272 2 1 3 CCB 272 3 2100 276 1 1 2 CCB 276 2 0011 289 1 2 3 CCB 289 3 1200 295 2 1 3 CCB 295 3 2010 302 2 2 CCB 302 2 0002 305 3 3...

Страница 7: ...050 650 4 1 5 CCB 650 5 0041 676 3 2 5 CCB 676 5 0032 702 2 3 5 CCB 702 5 0023 729 1 4 5 CCB 729 5 0014 748 6 6 CCB 748 6 0060 755 5 5 CCB 755 5 0005 775 5 1 6 CCB 775 6 0051 801 4 2 6 CCB 801 6 0042...

Страница 8: ...guration In this chapter is explained how to determine the dimensions of the cascade configuration and how much space is required in the room where the cascade configuration will be installed Figure 4...

Страница 9: ...AMPLES In case a cascade configuration for 275 kW is required which will exist of 2 boilers refer to Table 4 1 for the dimensions of the cascade configuration The table shows that frame length for thi...

Страница 10: ...L3 length low loss header 487 487 H1 height gas 308 308 H2 height header coupling 257 257 H3 height couplings 380 380 D1 header connection size DN 80 PN6 3 DN 80 PN6 3 D2 header connection size DN 80...

Страница 11: ...to the hydraulic and gas header groups Each connecting set contains one gas one supply and one return pipe More details can be found in chapter 6 5 Hydraulic and gas header group existing of 1 gas 1 s...

Страница 12: ...lve ball valve coupling to return header Figure 6 1 Connecting sets The gas connecting set should be connected to the gas connection on the boiler The supply connecting set must be connected to the bo...

Страница 13: ...2 Supply header red marking 3 Return header blue marking Figure 7 1 Parts hydraulic and gas header group 7 2 Support beam and support brackets Figure 7 2 Headers support beam and support brackets 1 2...

Страница 14: ...Depending on the cascade configuration the headers come in the following size varieties Header Varieties Gas header DN50 DN80 Water header supply and return DN65 DN80 DN100 See also Table 4 1 Table 4...

Страница 15: ...assembling the frame on which the boilers will be hung The basic frame exists of the following elements L shaped stands Top beam In between beam middle beam Mounting material bolts washers 1 Locking...

Страница 16: ...e 8 1 To mount the frame subsequently carry out the steps in the following procedure 1 Check after unpacking that all parts are actually present 2 Mount the in between beam s between the L stands Ensu...

Страница 17: ...eaders allow for some play tolerance for a neat installation After finishing the installation the support beam and brackets can be tightened 1 Mount the support beam s for the hydraulic and gas header...

Страница 18: ...et with the locking strip to prevent the boiler from falling off the bracket see drawing 5 Make sure that the boiler is at the right position near level The boilers must hang backwards slightly 1 0 5...

Страница 19: ...pplied with 2 flat seal two part couplings 1 flat seal coupling for connection to boiler inside thread female thread 1 flat seal coupling for connection to connecting set outside thread male thread a...

Страница 20: ...installation 540 to 930 kW E68 0300 503 200 x 200 x 5 Table 12 1 Low loss header connection sizes The low loss header can be fitted on the right hand side as well as on the left hand side without maki...

Страница 21: ...t be completed with all other necessary parts and connections This may include all valves non return valves strainers air separators expansion vessel overflow Attention The hydraulic piping of the Eco...

Страница 22: ...the Installation Service Manual of the CB boiler series Flue gas and air supply system For each boiler the combined resistance of the individual flue gas and air inlet pipe can be calculated and check...

Страница 23: ...ow to manage the parameters required for the cascade configuration is described in detail in the chapter s about Cascading in the Installation Service Manual of the CB boiler series Attention Changes...

Страница 24: ...re 5 1 Cascade parts and groups 11 Figure 6 1 Connecting sets 12 Figure 7 1 Parts hydraulic and gas header group 13 Figure 7 2 Headers support beam and support brackets 13 Figure 7 3 Headers and conne...

Страница 25: ...E93 9950EN CB Cascade manual 25 20 Appendix A Cascade Parts The following drawings give an overview of parts used in a cascade configuration Top view Front view 5 E67 5020 002...

Страница 26: ...N65 DN80 DN100 11 Low loss header DN65 DN80 DN100 12 Gas connecting set 13 Gas connecting set 1 14 Supply connecting set R1 15 Return connecting set R1 16 Supply connecting set R1 Return connecting se...

Страница 27: ......

Страница 28: ...Your distributor Eco Heating Systems Groningen B V P O Box 5145 9700 GC Groningen Rigaweg 10 9723 TH Groningen The Netherlands T 31 0 50 5470470 E sales ecohs nl I www ecohs nl...

Отзывы: