Before You Start
3.1
Overview
This chapter contains important information that will help you carry out a safe and trouble-free installation.
3.1.1
Outline of the Installation Procedure
The main steps involved in the installation of NPT-1020 equipment are described in the following table.
Consult your site installation plans for specific details.
Table
3-1: Typical NPT-1020 equipment installation sequence
No. Task
Reference
1
Prepare the installation site and check the physical location,
environmental compliance, and availability of power sources.
Before You Start
2
Prepare power, alarm, management, and transmission cables at the
installation site.
Before You Start and
Equipment Installation
3
Route the required power, alarm, management, and transmission
cables to the intended NPT-1020 equipment location.
Equipment Installation
4
If required, install the equipment racks.
Equipment Installation
5
Mark the location of each NPT-1020 shelf, EXT-2U shelf, and relevant
accessories (Fiber Storage Tray (FST), Optical Distribution Frame (ODF),
PCM Interconnection Panels (ICPs), and Digital Distribution Frame
(DDF) on each rack, in accordance with the site installation plan.
Notes:
For each NPT-1020, it is recommended that you leave at least 4 U
of space above the NPT-1020 shelf to enable future installation of
the EXT-2U shelf.
The NPT-1020 can only support balanced E1 interfaces directly.
For unbalanced E1s, the xDDF-21 patch panel must be configured,
which provides conversion between balanced and unbalanced E1s
for 21 x E1.
When PCM interfaces are provided by the SM_10E/EM_10E, the
corresponding ICPs can be installed in order to simplify
installation and connection to customer termination equipment.
Equipment Installation
6
When applicable, install the EMS-APT management station.
EMS-APT Installation
Manual
7
Install the Rack Alarm Panel (RAP) and other equipment needed in
each rack.
Installing the RAP-BG, or
8
Install the NPT-1020 shelves in the appropriate rack.