9395P-1200 Installation and Operation Manual 164000500—Rev 11
75
ATTENTION!
Lors de l’évaluation du système de batterie, ne pas dépasser les capacités internes du chargeur de batteries.
Se reporter au chapitre
sur les notices techniques pour connaître les
tensions maximales du chargeur de batteries.Ne pas installer une armoire endommagée. Signaler les
dommages au transporteur et communiquer avec un représentant du service Eaton immédiatement.
To install wiring to connections:
NOTE
An installed FI-UPM is always designated as UPM 4.
NOTE
Battery Cable Routing Requirements using Conduit
:
•
* Each conduit must have a Positive, Negative, and Ground conductor
•
* There must be an equal number of positive and negative conductors in a single
conduit. Only one ground conductor is required in each conduit.
•
Battery Cable Routing Requirements using Raceway:
•
* Positive and negative battery cables must be run side by side in the raceway in an
alternating pattern (+ - + - + - + -).
•
* There must be a ground cable running in the raceway with the battery cables.
1.
Route the battery cables between the ISBM section and the battery system or battery disconnect. See
,
,
, and
for wiring access information and terminal locations.
2.
If wiring the UPS for a common battery, proceed to Step 3; if wiring for a separate battery, proceed to Step
5.
3.
Using hardware from the external wiring terminal hardware kit (see
), connect the positive,
negative, and ground DC power wiring from the battery systems or disconnects to the ISBM section
battery and ground terminals. Use one set of terminals for each UPM as shown in
. See
paragraph for wiring and termination requirements.
4.
Proceed to Step 6.
5.
Using hardware from the external wiring terminal hardware kit (see
), connect the positive,
negative, and ground DC power wiring from the battery systems or disconnects to the ISBM section
battery and ground terminals. Use one set of terminals for each UPM. See paragraph
UPS System Power Wiring Preparation
for wiring and termination requirements.
6.
After wiring the UPS system to the facility power and critical load, be sure to ground the system according
to local and/or national electrical wiring codes.
7.
If wiring interface connections, proceed to paragraph
UPS System Interface Wiring Preparation
otherwise, proceed to Step 8.
8.
When all wiring is complete, reinstall the top and bottom safety shield panels removed in paragraph
External Power Wiring Installation
, Step 2. Secure with the retained hardware.
9.
Reinstall the left front panel removed in paragraph
External Power Wiring Installation
, Step 1 and
secure with the retained hardware.
Содержание Power Xpert 9395P-1100/1100
Страница 8: ......
Страница 28: ...10 Eaton Power Xpert 9395P 1200 Installation and Operation Manual 164000500 Rev 11 Introduction...
Страница 112: ...94 Eaton Power Xpert 9395P 1200 Installation and Operation Manual 164000500 Rev 11 UPS System Installation...
Страница 154: ...136 Eaton Power Xpert 9395P 1200 Installation and Operation Manual 164000500 Rev 11 Understanding UPS Operation...
Страница 202: ...184 Eaton Power Xpert 9395P 1200 Installation and Operation Manual 164000500 Rev 11 Communication...
Страница 210: ...192 Eaton Power Xpert 9395P 1200 Installation and Operation Manual 164000500 Rev 11 UPS Maintenance...
Страница 214: ...16400050011 164000500 11...